Project | Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSR at Komalapuram |
---|---|
Project Code | ALPGOK0317486P2 |
Type | Package |
Main Project | Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Construction of 3.5 LL capacity OHSR at Komalapuram |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 19200000 |
TS Number | TS/2018-2019/2018/3366 Dated: 23-05-2018 |
Technical specification | Construction of 3.5 LL capacity OHSR at Komalapuram Foundation-12 nos Pile foundation having 4 nos -700mm dia, 6 nos-800mm dia and 2 nos 900mm dia. Stage hight-17.50m |
Contractor | ROY VARGHESE (Mob: 9447488092) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/06/2020 |
---|---|
Scheduled date of Completion as per agreement | 30 Sep 2019 |
Expected date of Completion | 31/07/2021 |
TS Date | 23 May 2018 |
---|---|
Estimate Approval | 23 May 2018 |
NIT Approval | 14 Jun 2018 |
Supplying and Laying | 14 Jun 2018 |
Tender Closing | 13 Jul 2018 |
Technichal Pre-Qualification | 27 Sep 2018 |
Price bid opening | 27 Sep 2018 |
NA | 06 Sep 2018 |
---|---|
CE Approval | 17 Aug 2018 |
Head Office Approval | 17 Aug 2018 |
Board Approval | 17 Aug 2018 |
Final Approval | 17 Aug 2018 |
Workorder Date | 29 Aug 2018 |
Alappuzha Project Dn AE4 |
Date: 30/09/2021 |
Work has been completed | 100% Completed
trail running in progress.
Alappuzha Project Dn AE4 |
Date: 29/09/2021 |
Work in progress | 89% Completed
Interconnection works and valve fixing progressing.