Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Green Book-Aryad-Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main

Project Green Book-Aryad-Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main
Project Code ALPGOK0317486P1
Type Package
Main Project Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 23200000
TS Number TS/2018-2019/2018/3367 Dated: 23-05-2018
Technical specification Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main
Contractor ROY VARGHESE (Mob: 9447488092)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/11/2018
Scheduled date of Completion as per agreement 07 Sep 2019
Expected date of Completion 07/09/2019

Processing Dates

TS Date 23 May 2018
Estimate Approval 23 May 2018
NIT Approval 14 Jun 2018
Supplying and Laying 14 Jun 2018
Tender Closing 13 Jul 2018
Technichal Pre-Qualification 27 Jul 2018
Price bid opening 27 Jul 2018

Approval Dates

CE Approval 17 Aug 2018
Head Office Approval 17 Aug 2018
Board Approval 17 Aug 2018
Final Approval 17 Aug 2018
Workorder Date 29 Aug 2018
NA 06 Sep 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn AE4
Date: 05/02/2021

Work has been completed | 100% Completed

All pipe laying works completed and charged from existing distribution system from existing OHSR. The interconnection from new OHSR shall be done on commissioning of new 3.50 LL OHSR which is under construction.