Green Book-Aryad-Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main
Project |
Green Book-Aryad-Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main |
Project Code |
ALPGOK0317486P1 |
Type |
Package |
Main Project |
Green Book-2017-18-Augmentation of RWSS to Aryad Panchayath-Construction of 3.5 LL capacity OHSr at komalapuram and Supplying and Laying of Clear water Pumping main and distribution lines and connected works in Aryad Panchayath
|
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
Agreement Number |
|
Agreement Date |
|
TS Amount (Rs) |
23200000 |
TS Number |
TS/2018-2019/2018/3367 Dated: 23-05-2018 |
Technical specification |
Supplying and laying of distributino line 200 mm HDPE-2000m, 160 mm PVC 8 Kg-3000m, 110 mm PVC pipe 8 Kg-1000m, 90 mm PVC pipe 8 Kg-11000m and 200 mm DI K9 pipe 285m as clear water pumping main |
Contractor |
ROY VARGHESE (Mob: 9447488092) |
No project review have been added to this project
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
Date of start of Package |
18/11/2018 |
Scheduled date of Completion as per agreement |
07 Sep 2019 |
Expected date of Completion |
07/09/2019 |
Processing Dates
TS Date |
23 May 2018 |
Estimate Approval |
23 May 2018 |
NIT Approval |
14 Jun 2018 |
Supplying and Laying |
14 Jun 2018 |
Tender Closing |
13 Jul 2018 |
Technichal Pre-Qualification |
27 Jul 2018 |
Price bid opening |
27 Jul 2018 |
Approval Dates
CE Approval |
17 Aug 2018 |
Head Office Approval |
17 Aug 2018 |
Board Approval |
17 Aug 2018 |
Final Approval |
17 Aug 2018 |
Workorder Date |
29 Aug 2018 |
NA |
06 Sep 2018 |
Other details
Project Schedule |
View |
Project Components |
View |
Project Officers |
View |
Alappuzha Project Dn AE4 |
Date: 05/02/2021 |
Work has been completed | 100% Completed
All pipe laying works completed and charged from existing distribution system from existing OHSR. The interconnection from new OHSR shall be done on commissioning of new 3.50 LL OHSR which is under construction.