AMRUT - Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranallor in Kohi Corporation 2016-17
Project |
AMRUT - Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranallor in Kohi Corporation 2016-17 |
Project Code |
EKMAMRUT0917893 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranallor |
Status |
Completed |
District |
Ernakulam |
Executing Office |
Kochi Project Division |
AS Amount (Rs) |
77500000
|
AS Number |
GO(Rt) NO: 2800/2017/LSGD |
TS Amount (Rs) |
50000000 |
TS Number |
TS/CE/CR/KWA/59/2017-18 |
Total Bill Submitted (Rs) |
49238833 |
Total Bill Paid (Rs) |
49238833 |
Population Benefitted |
23520 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
31 Jan 2022 |
Coverage |
Kunnumpuram North & Peeliyadu |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor. |
Kochi Project Division |
|
2 |
AMRUT Projects 2016-17 - Supply, Erection, Testing and commissioning of Pump sets having a discharge of 126 lps against a head of 25 m and allied works at 15 LL OHSR, Vadathodu, Cheranelloor |
Kochi Project Division |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Feb 2022 |
Work completed |
Kochi WS Project Dn AE 1 |
|
28 Jan 2022 |
Interlocking tiles laying near completion |
Kochi WS Project Dn AE 1 |
|
29 Dec 2021 |
Compound wall, gate, painting etc in progress |
Kochi WS Project Dn AEE-2 |
|
09 Dec 2021 |
Balance Compound wall,drain ,gate,painting etc in progress |
Kochi WS Project Dn AEE-2 |
|
30 Nov 2021 |
Site levelling and clearing work and construction of soak pit in progress |
Kochi JNNURM AEE-3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/12/2018 |
Scheduled date of Completion of the Project |
21 Dec 2019 |
Expected date of Completion |
31/01/2022 |
Processing Dates
AS Date |
27 Sep 2017 |
TS Date |
23 Jan 2018 |