Project | AMRUT-Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor. |
---|---|
Project Code | EKMAMRUT0917893P2 |
Type | Package |
Main Project | AMRUT - Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranallor in Kohi Corporation 2016-17 |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor. |
Status | On-going |
District | Ernakulam |
Executing Office | Kochi Project Division |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 50000000 |
TS Number | TS/CE/CR/KWA/59/2017-18 |
Technical specification | Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor. |
Contractor | M.J. THOMAS (Mob: 8921217442) |
Issue date | Solved On | Action Taken On | Category | Description | Comments | Issue Status |
---|---|---|---|---|---|---|
05 Oct 2021 | 25 Oct 2021 | Pending | Risks From Other Projects | The pump set erection arranged as separate contract. and is delayed by the contractor. | Pump set erection started on 25/10/2021 | Solved |
01 Oct 2021 | Pending | Pending | Social Project Risks | The original proposal was to connect the overflow /scour pipes to the drain behind the compound. In the final stage, residents, Corporation councillor erc objected. MLA, MAYOR, KWA higher officials involved to resolve it but they have not yielded and decided to take the drain through main road to Vadathode as additional work costing about 26 Lakhs. PWD, Traffic permission etc was needed for this additional work | No comments available. | Pending |
01 Oct 2021 | Pending | 07 Oct 2021 | Risks From Other Projects | The original proposal was to connect the overflow /scour pipes to the drain behind the compound. In the final stage, residents, Corporation councillor erc objected. MLA, MAYOR, KWA higher officials involved to resolve it but they have not yielded and decided to take the drain through main road to Vadathode as additional work costing about 26 Lakhs. PWD, Traffic permission etc was needed for this additional work | No comments added. | Action Taken |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/12/2018 |
---|---|
Scheduled date of Completion as per agreement | 21 Dec 2019 |
Expected date of Completion | 31/01/2022 |
TS Date | 23 Jan 2018 |
---|---|
Estimate Approval | 23 Jan 2018 |
NIT Approval | 08 Nov 2018 |
Tender Closing | 22 Nov 2018 |
Technichal Pre-Qualification | 26 Nov 2018 |
Price bid opening | 26 Nov 2018 |
NA | 04 Jan 2019 |
---|---|
Workorder Date | 22 Dec 2018 |
Kochi WS Project Dn AE 1 |
Date: 31/01/2022 |
Kochi WS Project Dn AE 1 |
Date: 29/01/2022 |
Work in progress | 99% Completed
No work .