AMRUT-Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor.

Project AMRUT-Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor.
Project Code EKMAMRUT0917893P2
Type Package
Main Project AMRUT - Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranallor in Kohi Corporation 2016-17
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor.
Status On-going
District Ernakulam
Executing Office Kochi Project Division
Agreement Number
Agreement Date
TS Amount (Rs) 50000000
TS Number TS/CE/CR/KWA/59/2017-18
Technical specification Construction of 15LL OHSR and 2LL CWR at Vadathode, Cheranalloor.
Contractor M.J. THOMAS (Mob: 8921217442)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
05 Oct 2021 25 Oct 2021 Pending Risks From Other Projects The pump set erection arranged as separate contract. and is delayed by the contractor. Pump set erection started on 25/10/2021 Solved
01 Oct 2021 Pending Pending Social Project Risks The original proposal was to connect the overflow /scour pipes to the drain behind the compound. In the final stage, residents, Corporation councillor erc objected. MLA, MAYOR, KWA higher officials involved to resolve it but they have not yielded and decided to take the drain through main road to Vadathode as additional work costing about 26 Lakhs. PWD, Traffic permission etc was needed for this additional work No comments available. Pending
01 Oct 2021 Pending 07 Oct 2021 Risks From Other Projects The original proposal was to connect the overflow /scour pipes to the drain behind the compound. In the final stage, residents, Corporation councillor erc objected. MLA, MAYOR, KWA higher officials involved to resolve it but they have not yielded and decided to take the drain through main road to Vadathode as additional work costing about 26 Lakhs. PWD, Traffic permission etc was needed for this additional work No comments added. Action Taken

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/12/2018
Scheduled date of Completion as per agreement 21 Dec 2019
Expected date of Completion 31/01/2022

Processing Dates

TS Date 23 Jan 2018
Estimate Approval 23 Jan 2018
NIT Approval 08 Nov 2018
Tender Closing 22 Nov 2018
Technichal Pre-Qualification 26 Nov 2018
Price bid opening 26 Nov 2018

Approval Dates

NA 04 Jan 2019
Workorder Date 22 Dec 2018

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kochi WS Project Dn AE 1
Date: 31/01/2022

Work has been completed | 100% Completed

Interlocking tile laying completed.

Attached images

img

Kochi WS Project Dn AE 1
Date: 29/01/2022

Work in progress | 99% Completed

No work .