Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Feb 2022 | Work completed | Kochi WS Project Dn AE 1 | |
28 Jan 2022 | Interlocking tiles laying near completion | Kochi WS Project Dn AE 1 | |
29 Dec 2021 | Compound wall, gate, painting etc in progress | Kochi WS Project Dn AEE-2 | |
09 Dec 2021 | Balance Compound wall,drain ,gate,painting etc in progress | Kochi WS Project Dn AEE-2 | |
30 Nov 2021 | Site levelling and clearing work and construction of soak pit in progress | Kochi JNNURM AEE-3 | |
25 Nov 2021 | Water supply from the OHSR to Cheranelloor commenced from 18.11.2021 on alternate days intermittently as per the present inflow conditions. | Kochi WS Project Dn AEE-2 | |
24 Nov 2021 | Chamber cover slab concreting and other finishing works in progress | Kochi WS Project Dn AEE-2 | |
20 Nov 2021 | out let valve chamber construction, painting works and other finishing works are going on | Kochi WS Project Dn AEE-2 | |
17 Nov 2021 | flow meter and out let valve chamber construction, filling of OHSR from the sump, fixing of rain water out let pipe and painting works are going on | Kochi WS Project Dn AEE-2 | |
14 Nov 2021 | final finishing work like painting and flooring of pumphouse,level indicator intallation,chamber construction ,yard levelling going on | Kochi WS Project Dn AEE-2 |