Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Feb 2022 Work completed Kochi WS Project Dn AE 1
28 Jan 2022 Interlocking tiles laying near completion Kochi WS Project Dn AE 1
29 Dec 2021 Compound wall, gate, painting etc in progress Kochi WS Project Dn AEE-2
09 Dec 2021 Balance Compound wall,drain ,gate,painting etc in progress Kochi WS Project Dn AEE-2
30 Nov 2021 Site levelling and clearing work and construction of soak pit in progress Kochi JNNURM AEE-3
25 Nov 2021 Water supply from the OHSR to Cheranelloor commenced from 18.11.2021 on alternate days intermittently as per the present inflow conditions. Kochi WS Project Dn AEE-2
24 Nov 2021 Chamber cover slab concreting and other finishing works in progress Kochi WS Project Dn AEE-2
20 Nov 2021 out let valve chamber construction, painting works and other finishing works are going on Kochi WS Project Dn AEE-2
17 Nov 2021 flow meter and out let valve chamber construction, filling of OHSR from the sump, fixing of rain water out let pipe and painting works are going on Kochi WS Project Dn AEE-2
14 Nov 2021 final finishing work like painting and flooring of pumphouse,level indicator intallation,chamber construction ,yard levelling going on Kochi WS Project Dn AEE-2