Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
16 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
12 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
11 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
10 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
08 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
06 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
05 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
04 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3
03 Aug 2022 All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. Palakkad Proj AE 3