| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 16 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 12 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 11 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 10 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 08 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 06 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 05 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 04 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 | |
| 03 Aug 2022 | All structural works completed at Intake well cum pump house, Booster station, 12.00mld WTP. Electromechanical& Pipeline& Finishing works are to be completed.Balnce RWPM of 400DI& CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump test completed& yet to reach the location.CWPS to be supplied. | Palakkad Proj AE 3 |