| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 May 2022 | Excavation and pipe laying work towards main road is in progress. 470 m pipe laid and 29 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 04 May 2022 | Excavation and pipe laying work towards main road is in progress. 450 m pipe laid and 28 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 28 Apr 2022 | Excavation and pipe laying work towards main road is in progress. 430 m pipe laid and 25 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 27 Apr 2022 | Excavation and pipe laying work towards main road is in progress. 430 m pipe laid and 25 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 25 Apr 2022 | Excavation and pipe laying work towards main road is in progress. 405 m pipe laid and 23 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 24 Apr 2022 | Excavation and pipe laying work towards main road is in progress.390 m pipe laid and 22 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 22 Apr 2022 | Excavation and pipe laying work towards main road is in progress.390 m pipe laid and 22 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 20 Apr 2022 | Excavation and pipe laying work towards main road is in progress.375 m pipe laid and 21 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 18 Apr 2022 | Pipe jointing work is in progress. | Plamoodu Sewerage Project Sn AE | |
| 14 Apr 2022 | Pipe jointing work is in progress. | Plamoodu Sewerage Project Sn AE |