Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jan 2026 18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
24 Dec 2025 18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
17 Dec 2025 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
12 Dec 2025 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
01 Dec 2025 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
20 Nov 2025 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
07 Nov 2025 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
23 Oct 2025 17.8 km of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
22 Oct 2025 17.8 m of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE
16 Oct 2025 17.8 m of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress Thalassery PH Sn AE