| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Jan 2026 | 18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 24 Dec 2025 | 18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 17 Dec 2025 | 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 12 Dec 2025 | 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 01 Dec 2025 | 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 20 Nov 2025 | 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 07 Nov 2025 | 17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 23 Oct 2025 | 17.8 km of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 22 Oct 2025 | 17.8 m of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE | |
| 16 Oct 2025 | 17.8 m of pipeline laid and FHTC -580 HTC -314 are given. Interconnection work, GSB & concrete work in progress | Thalassery PH Sn AE |