| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Jul 2025 | 17.8 m of pipeline laid and FHTC -390 HTC -434 are given. Work in progress | Thalassery PH Sn AE | |
| 16 Jul 2025 | 17.8 m of pipeline laid and FHTC -390 HTC -434 are given. Work in progress | Thalassery PH Sn AE | |
| 27 Jun 2025 | 17154 m of pipeline laid and FHTC -355 HTC -395 are given. Work in progress | Thalassery PH Sn AE | |
| 17 Jun 2025 | 17154 m of pipeline laid and FHTC -350 HTC -390 are given. Work in progress | Thalassery PH Sn AE | |
| 03 Jun 2025 | 16933 m of pipeline laid and FHTC -108 HTC -720 are given. Work in progress | Thalassery PH Sn AE | |
| 19 May 2025 | 16933 m of pipeline laid and FHTC -108 HTC -720 are given. Work in progress | Thalassery PH Sn AE | |
| 10 May 2025 | 16113 m of pipeline laid and FHTC -100 HTC -490 are given. Work in progress | Thalassery PH Sn AE | |
| 01 May 2025 | 15353 m of pipeline laid and FHTC -100 HTC -490 are given. Work in progress | Thalassery PH Sn AE | |
| 15 Apr 2025 | 14874 m of pipeline laid and FHTC -100 HTC -458 are given. Work in progress | Thalassery PH Sn AE | |
| 06 Apr 2025 | 14487 m of pipeline laid and FHTC -100 HTC -458 are given. Work in progress | Thalassery PH Sn AE |