| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Nov 2024 | 8547 m of pipeline laid and 23 FHTC 142 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 14 Nov 2024 | 8547 m of pipeline laid and 23 FHTC 142 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 07 Nov 2024 | 8301 m of pipeline laid and 23 FHTC 115 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 04 Nov 2024 | 8301 m of pipeline laid and 23 FHTC 115 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 01 Nov 2024 | 8283 m of pipeline laid and 23 FHTC 115 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 26 Oct 2024 | 8187 m of pipeline laid and 23 FHTC 115 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 24 Oct 2024 | 8187 m of pipeline laid and 23 FHTC 115 HTC are given. Work in progress | Thalassery PH Sn AE | |
| 22 Oct 2024 | 7947 m of pipeline laid 115HTCs, 23FHTCs given . | Kannur PH Dn EE | |
| 21 Oct 2024 | 7947 m of pipeline laid and 6 FHTC are given. Work in progress | Thalassery PH Sn AE | |
| 17 Oct 2024 | 4300 m of pipeline laid and 6 FHTC are given. Work in progress. | Thalassery PH Sn AE |