Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work
| Project |
Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
| Project Code |
KNRAMRUT 2112214162 |
| Type |
Main project |
| Funding Agency |
AMRUT 2 |
| Category |
AMRUT 2 |
| Type of scheme |
Water Supply |
| Scheme |
|
| Description |
Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
| Status |
On-going |
| District |
Kannur |
| Executing Office |
Thalassery PH Sub Dn |
| AS Amount (Rs) |
275650000
|
| AS Number |
G.O.(Rt)No.2906/2022/LSGD |
| TS Amount (Rs) |
62030000 |
| TS Number |
17439/2022-2023 |
| Total Bill Submitted (Rs) |
9304336 |
| Total Bill Paid (Rs) |
8791806 |
| Population Benefitted |
5678 |
| Capacity in MLD |
2.00 |
| Actual Project Completion Date |
Date is not specified |
| Coverage |
Wards 1 to 9 |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
Thalassery PH Sn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 05 Jan 2026 |
18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress |
Thalassery PH Sn AE |
|
| 24 Dec 2025 |
18.175 km of pipeline laid and FHTC -946 HTC -204 are given. Interconnection work, GSB & concrete work in progress |
Thalassery PH Sn AE |
|
| 17 Dec 2025 |
17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress |
Thalassery PH Sn AE |
|
| 12 Dec 2025 |
17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress |
Thalassery PH Sn AE |
|
| 01 Dec 2025 |
17.817 km of pipeline laid and FHTC -613 HTC -366 are given. Interconnection work, GSB & concrete work in progress |
Thalassery PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
13/11/2023 |
| Scheduled date of Completion of the Project |
12 Jul 2024 |
| Expected date of Completion |
31/12/2024 |
Processing Dates
| AS Date |
24 Nov 2022 |
| TS Date |
25 Mar 2023 |