| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Apr 2024 | 1948.2 m of pipeline laid. Work in progress. | Thalassery PH Sn AE | |
| 24 Apr 2024 | 1422.2 m of pipeline laid. Work in progress. | Thalassery PH Sn AE | |
| 20 Apr 2024 | 1422.2 m of pipeline laid. Work in progress. | Thalassery PH Sn AE | |
| 12 Apr 2024 | 1164 m of pipeline laid. Work in progress. | Thalassery PH Sn AE | |
| 02 Apr 2024 | 802m pipeline laid. | Kannur PH Dn EE | |
| 25 Mar 2024 | Pipe supplied. | Kannur PH Dn EE | |
| 13 Mar 2024 | Pipe supplied. | Thalassery PH Sn AE | |
| 28 Feb 2024 | Pipe supplied. | Kannur PH Dn EE | |
| 24 Feb 2024 | Pipe supplied | Thalassery PH Sn AE | |
| 14 Feb 2024 | Agreement executed on 03.11.2023 | Kannur PH Dn EE |