Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 May 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2132m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =657.4m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
29 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2132m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =657.4m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
27 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2132m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =657.4m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
25 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2132m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =657.4m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
22 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2132m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =657.4m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
20 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2120m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =647.8m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
17 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2120m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =568.2m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
13 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2120m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =568.2m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
10 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2120m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =544m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3
08 Apr 2026 KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=633.1m,90/6kg=8554m,90/8kg=2120m,110/8kg=430.2m,110/6kg=1180m,140/6 kg=666m,250mm DI=633.5m,350mm DI=2985.5m,160/6Kg=668m,80mm GI =544m,300mm DI=121m,100mm GI=39.7M Chittur Project Dn - AE 3