Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Jan 2025 PHASE II PACKAGE I Work in progress | 91% Completed | 09/01/2025 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II PACKAGE II PART II Not Started | 09/01/2025 Kannambra low level - New estimate submitted to KIIFB for TS approval PHASE II PACKAGE III Work in progress | 85% Completed | 09/01/2025 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.765 km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2580 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M PHASE II PACKAGE II PART I Work in progress | 72% Completed | 09/01/2025 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
03 Jan 2025 PHASE II PACKAGE I Work in progress | 91% Completed | 03/01/2025 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid, GAP filling work is in progress. PHASE II PACKAGE II PART II Not Started | 03/01/2025 Not Started Kannambra low level - New estimate submitted to KIIFB for TS approval PHASE II PACKAGE III Work in progress | 85% Completed | 03/01/2025 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.765 km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2580 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M PHASE II PACKAGE II PART I Work in progress | 72% Completed | 03/01/2025 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
31 Dec 2024 PHASE II PACKAGE I Work in progress | 91% Completed | 31/12/2024OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progressPHASE II PACKAGE II PART IINot Started | 31/12/2024Kannambra low level - New estimate submitted to KIIFB for TS approvalPHASE II PACKAGE IIIWork in progress | 85% Completed | 31/12/2024Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.765 km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2580 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807MPHASE II PACKAGE II PART I Work in progress | 72% Completed | 31/12/2024work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
20 Dec 2024 Phase II Package I Work in progress | 91% Completed | 20/12/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 20/12/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II Package III Work in progress | 85% Completed | 20/12/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.765 km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2580 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part I Work in progress | 72% Completed | 20/12/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
11 Dec 2024 Phase II Package I Work in progress | 91% Completed | 11/12/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 11/12/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II Package III Work in progress | 85% Completed | 11/12/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.765 km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2580 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part I Work in progress | 72% Completed | 11/12/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
03 Dec 2024 Phase II Package I Work in progress | 91% Completed | 03/12/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 03/12/2024 Not Started | 08/11/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II Package III Work in progress | 85% Completed | 03/12/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.717km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part I Work in progress | 72% Completed | 03/12/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
23 Nov 2024 Phase II Package I Work in progress | 91% Completed | 23/11/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 23/11/2024 Not Started | 08/11/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II Package III Work in progress | 85% Completed | 23/11/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.717km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part I Work in progress | 72% Completed | 23/11/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
16 Nov 2024 Phase II Package I Work in progress | 91% Completed | 16/11/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 16/11/2024 Not Started | 08/11/2024 kannambra low level - New estimate subited to KIIFB for TS approval Phase II Package III Work in progress | 85% Completed | 16/11/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.717km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part III Work in progress | 72% Completed | 16/11/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
08 Nov 2024 Phase II Package I Work in progress | 91% Completed | 08/11/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 08/11/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II Package III Work in progress | 85% Completed | 08/11/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.717km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M Phase II Package II Part III Work in progress | 72% Completed | 08/11/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3
01 Nov 2024 PHASE II PACKAGE I Work in progress | 91% Completed | 01/11/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II PACKAGE 2 PART II Not Started | 01/11/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL PHASE II PACKAGE III Work in progress | 85% Completed | 01/11/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 102.717km /out of 120km , 1.) 90 mm 6 kg 49350m supplied- 34166 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1772.5 m supplied-493.5 M,18)300MM DI-807M PHASE II PACKAGE II PART III Work in progress | 72% Completed | 01/11/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing Chittur Project Dn - AE 3