| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Sep 2024 | PHASE II PACKAGE I Work in progress | 91% Completed | 26/09/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II PACKAGE II Not Started | 26/09/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL PHASE II PACKAGE III Work in progress | 85% Completed | 26/09/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.975km /out of 120km , 1.) 90 mm 6 kg 48780 m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1671 m supplied-493.5 M PHASEII PACKAGE II PART I Work in progress | 72% Completed | 19/09/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 19 Sep 2024 | Phase II Package I Work in progress | 91% Completed | 19/09/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Not Started | 19/09/2024 kannambra low level - New estimate subited to KIIFB for TS approvaL Phase II PPackage III Work in progress | 85% Completed | 19/09/2024 Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.975km /out of 120km , 1.) 90 mm 6 kg 48780 m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1671 m supplied-493.5 M Phase II Pcakge II Part I Work in progress | 72% Completed | 19/09/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 13 Sep 2024 | Phase II PACKAGE I Work in progress | 91% Completed | 13/09/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II PACKAGE II PART I Not Started | 13/09/2024 kannambra low level - New estimate subited to KIIFB for TS approva Work in progress | 85% Completed | 13/09/2024 PHASE II PACKAGE III 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.665 km /out of 120km , 1.) 90 mm 6 kg 48624 m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1517 m supplied-493.5 M PHASE II PACKAGE II PART I Work in progress | 72% Completed | 13/09/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 06 Sep 2024 | PHASE II PACKAGE I Work in progress | 91% Completed | 06/09/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II PACKAGE II PART II Not Started | 06/09/2024 kannambra low level - New estimate subited to KIIFB for TS approval PHASE II PACKAGE III Work in progress | 85% Completed | 06/09/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M PHASE II PACKAGE II PART I Work in progress | 72% Completed | 06/09/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 30 Aug 2024 | Phase II Package I Work in progress | 91% Completed | 30/08/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part II Not Started | 30/08/2024 kannambra low level - New estimate subited to KIIFB for TS approval Phase II Package III Work in progress | 85% Completed | 30/08/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M Phase II Package II Part IWork in progress | 72% Completed | 30/08/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 23 Aug 2024 | Package I Work in progress | 91% Completed | 23/08/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase II Package II Part IINot Started | 23/08/2024 kannambra low level - New estimate subited to KIIFB for TS approval Phase II Package III Work in progress | 85% Completed | 23/08/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M PhaseII Package II Part I Work in progress | 72% Completed | 23/08/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 14 Aug 2024 | PHASE-2-PACK-1 Work in progress | 91% Completed | 14/08/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-2-PART-2 Not Started | 14/08/2024 kannambra low level - New estimate subited to KIIFB for TS approval PHASE-2-PACK-3 Work in progress | 85% Completed | 14/08/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M PART-1 Work in progress | 72% Completed | 14/08/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing | Chittur Project Dn - AE 3 | |
| 09 Aug 2024 | Package 2 Not Started | 09/08/2024 kannambra low level - New estimate subited to KIIFB for TS approval package 3 Work in progress | 85% Completed | 09/08/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M Package 2 part 1 Work in progress | 72% Completed | 09/08/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing package 1 Work in progress | 91% Completed | 09/08/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress | Chittur Project Dn - AE 3 | |
| 02 Aug 2024 | PACKAGE IWork in progress | 91% Completed | 02/08/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACKAGE II PART I Work in progress | 72% Completed | 02/08/2024 work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing PACKAGE III Work in progress | 85% Completed | 02/08/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M | Chittur Project Dn - AE 3 | |
| 29 Jul 2024 | PACK-1 Work in progress | 91% Completed | 29/07/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-3 Culvert gap fillng work , 300 mm DI pipelaying work, RCC pipe carriying bridge along canal river , road restoration work are balance 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37386m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2532 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1434.5 m supplied-493.5 M Pack2 part-1 Work in progress | 72% Completed | 29/07/2024 2.) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing pack-2-part-2 Not Started | 29/07/2024 kannambra low level - New estimate subited to KIIFB for TS approval | Chittur Project Dn - AE 3 |