- Home
- Vandazhi, Kizhakkencherry, Vadakkencherr...
Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
| Project |
Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District |
| Project Code |
PKDKIIFB1118631 |
| Type |
Main project |
| Category |
KIIFB |
| Description |
The project is designed to provide adequate drinking water to the entire population of all wards except the elevated places of Vandazhy, Kizhakkanchery, Vadakkanchery and Kannambra Panchayaths in Alathur and Tharur constituencies of Palakkad district.The proposed project includes the components for pumping treated water to the proposed OHSR at Ponkandam and gravity feeding from balancing reservoir at WTP plant site to the proposed OHSRs at Cheerakuzhy palam, Vadakkanchery and Kannambra and boosting pumping from Cheerakuzhy to existing OHSR at Kanichiparutha so as to meet the water demand of the benefitted panchayaths at the rate of 100 liters per capita per day in the design year 2050. The Executive Engineer, Project Division, Palakkad vide letter no KWA/WSP/PKD/D2-01/2014 (Mangalam) dated 17.07.2019 has informed the Superintending Engineer, PPD, Kozhikkode that the proposed tank site at PWD rest house not available. Sri K D Prasenan, Hon'ble MLA of Alathur constituency, directed for ensuring the water supply coverage to the people residing in the high level areas of the benefitted Panchayaths in the meeting held at the chamber of honorable minister Sri. A K. Balan. Hence new tank locations are identified which will ensure the water supply coverage of the high level and low level zones of all 4 Grama panchayaths and design was modified accordingly by PPD. Location of service reservoirs are finalized for design based on the joint inspection of PPD and Project Division, Palakkad.The original proposal of transmission of treated water to OHSRs through gravity changed to Pumping. Hence motor pumpsets introduced in the revised proposal for pumping of treated water to the OHSRs. Due to the rezoning of the entire benfitted area in to 8 zones, the locations and capacities of proposed OHSRs are changed. The locations and revised capacities of OHSRs are 22 LL at Karimkunnam for covering the low level zones of Vadakkenchery and Kannambra panchayaths, 16 LL OHSR at Kavalupara Nannagadi for high level zones of Vandazhy and Kizhakkenchery panchayaths, 10LL OHSR at Palakuzhy for high level zones of Vadakkenchery and Kannambra, 0.20 LL OHSR capacity at a level of +507.000m to cater the demand of Palakuzhy highly elevated areas. The change in the diameter of transmission mains, length, route etc occurred. For pumping clear water from the Palakuzhy OHSR at a level of +187.00m to the 0.20LL OHSR at +507.00m, and two online booster stations are proposed. |
| District |
Palakkad |
| Execution |
Project Division Chittur |
| AS Amount (Rs) |
695400000.00 |
| Total Bill Submitted (Rs) |
-- |
| Total Bill Paid (Rs) |
-- |
| Coverage |
Vandazhy,vadakkenchery ,kizhakkenchery |
| Work Plan |
Download |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 29 Apr 2021 |
Package-1
Work in progress | 23% Completed | 29/04/2021
1.) 350mm DI pipe laid for a length of 4030.00m 2). column above plinth beam concrete work in progress.
Package-II-PART-i
Work in progress | 14% Completed | 29/04/2021
Vadakkencherry distribution network- (Vadakkenchery-thenidukke Road+ nayarthara road+anakkapara to thekupadam road+chinakkapadam to old NH road+old nh+diana side road +ridermain) 90mm 6kg 2952.00 m laid, 90mm 8 kg- 2991m laid and 160mm 8kg 102m laid. 80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 200 mm DI K9-390.50M
|
AE3 |
|
| 28 Apr 2021 |
PHASE-II-package-I
Work in progress | 23% Completed | 28/04/2021
1.) 350mm DI pipe laid for a length of 3400.00m 2). column above plinth beam shuttering and reinforcement work in progress.
2.)
PHASE-II-Package-ii-part-I
Work in progress | 14% Completed | 28/04/2021
Vadakkencherry distribution network- (Vadakkenchery-thenidukke Road+ nayarthara road+anakkapara to thekupadam road+chinakkapadam to old NH road+old nh+diana side road +ridermain) 90mm 6kg 2952.00 m laid, 90mm 8 kg- 2991m laid and 160mm 8kg 102m laid. 80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 200 mm DI K9-390.50M
|
AE3 |
|
| 20 Apr 2021 |
Work in progress | 22% Completed | 20/04/2021
Plinth beam concrete work completed ,Casting of columns above plinth beam reinforcement work started and 350mm DI pipe laid for a length of 2716.50m |
AE3 |
|
| 17 Apr 2021 |
Work in progress | 22% Completed | 17/04/2021
350 mm DI pipe laid for a length of 2716.50 m |
AE3 |
|
| 13 Apr 2021 |
package-I
Work in progress | 22% Completed | 13/04/2021
plinth beam concrete work in progress and pumping main 350 mm DI pipe laid for a length of 2418.00 m
package-II-part-I
Work in progress | 14% Completed | 13/04/2021
Vadakkencherry distribution network- Anakkappara- Mudappallur PWD Road: 90mm 6kg 990m laid, 90mm 8 kg-456m laid and 160mm 8kg 102m laid. vadakkanchery nayarthara road-90mm pvc 6 kg-132 m laid pulinkootam royal jn road-80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 90mm pvc 8 kg-1112m laid 110mm pvc-6 kg-1212.40 laid
|
AE3 |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 10 Feb 2021 |
Pending |
Pending |
Clearance from other department |
No comments available. |
Pending |
| 09 Feb 2021 |
Pending |
Pending |
Package I - construction of 22 LL OHSR at Karimkunnam - The land for the constrution of OHSr belong sto private party. The WRD order and revenue order obtained for LA under LARR act 2013. The application submitted to District collector. The demand note for remitting contingency charge showing rough amount of acquisition as 5.88 crores received. Allotted amount for land acquisition is only one crore from KIIFB. Shortage of enough amount for completing the LA Procedure |
No comments available. |
Pending |
| 09 Feb 2021 |
Pending |
Pending |
Clearance from other department |
No comments available. |
Pending |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work |
Project Division Chittur |
|
| 2 |
KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1 |
Project Division Chittur |
|
| 3 |
KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-II-Part-I-Supplying laying testing commissioning and maintenance of distribution net work from 22 LL OHSR at Karimkunnam and Transmission main from OHSR up to Diana Hotel including NH 544 crossing for kannambra low level zone and road restoration |
Project Division Chittur |
|
| 4 |
KIIFB 2017-2018-WSS to quality affected habitations of vandazhi, Kizhakkanchery and Vadakkanchery Gramapanchayath Phase II-Package-2-part-II |
Project Division Chittur |
|
Duration & Sanction dates
| Date of Sanction |
19/11/2018 |
| Date of start |
13/03/2020 |
| Expected date of Completion |
04/11/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
KIIFB |
Processing Dates
| Administrative Sanction[AS] |
19 Nov 2018 |
| Technichal Sanction[TS] |
13 Dec 2019 |
| Estimate Approval |
13 Dec 2019 |
| NIT Approval |
06 Mar 2020 |
| Supplying and Laying |
15 Jun 2020 |
| Tender Closing |
18 Jan 2020 |
| Technichal Pre-Qualification |
31 Jan 2020 |
| Price bid opening |
07 Feb 2020 |
Approval Dates
| Head Office Approval |
06 Jun 2020 |
| Board Approval |
18 Feb 2020 |
| Final Approval |
06 Mar 2020 |
| Workorder Date |
13 Mar 2020 |
| Agreement Date |
23 Mar 2020 |