Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District

Project Vandazhi, Kizhakkencherry, Vadakkencherry & Kannambra Comprehensive Fresh Water distribution project – Phase II in Palakkad District
Project Code PKDKIIFB1118631
Type Main project
Category KIIFB
Description The project is designed to provide adequate drinking water to the entire population of all wards except the elevated places of Vandazhy, Kizhakkanchery, Vadakkanchery and Kannambra Panchayaths in Alathur and Tharur constituencies of Palakkad district.The proposed project includes the components for pumping treated water to the proposed OHSR at Ponkandam and gravity feeding from balancing reservoir at WTP plant site to the proposed OHSRs at Cheerakuzhy palam, Vadakkanchery and Kannambra and boosting pumping from Cheerakuzhy to existing OHSR at Kanichiparutha so as to meet the water demand of the benefitted panchayaths at the rate of 100 liters per capita per day in the design year 2050. The Executive Engineer, Project Division, Palakkad vide letter no KWA/WSP/PKD/D2-01/2014 (Mangalam) dated 17.07.2019 has informed the Superintending Engineer, PPD, Kozhikkode that the proposed tank site at PWD rest house not available. Sri K D Prasenan, Hon'ble MLA of Alathur constituency, directed for ensuring the water supply coverage to the people residing in the high level areas of the benefitted Panchayaths in the meeting held at the chamber of honorable minister Sri. A K. Balan. Hence new tank locations are identified which will ensure the water supply coverage of the high level and low level zones of all 4 Grama panchayaths and design was modified accordingly by PPD. Location of service reservoirs are finalized for design based on the joint inspection of PPD and Project Division, Palakkad.The original proposal of transmission of treated water to OHSRs through gravity changed to Pumping. Hence motor pumpsets introduced in the revised proposal for pumping of treated water to the OHSRs. Due to the rezoning of the entire benfitted area in to 8 zones, the locations and capacities of proposed OHSRs are changed. The locations and revised capacities of OHSRs are 22 LL at Karimkunnam for covering the low level zones of Vadakkenchery and Kannambra panchayaths, 16 LL OHSR at Kavalupara Nannagadi for high level zones of Vandazhy and Kizhakkenchery panchayaths, 10LL OHSR at Palakuzhy for high level zones of Vadakkenchery and Kannambra, 0.20 LL OHSR capacity at a level of +507.000m to cater the demand of Palakuzhy highly elevated areas. The change in the diameter of transmission mains, length, route etc occurred. For pumping clear water from the Palakuzhy OHSR at a level of +187.00m to the 0.20LL OHSR at +507.00m, and two online booster stations are proposed.
District Palakkad
Execution Project Division Chittur
AS Amount (Rs) 695400000.00
Total Bill Submitted (Rs) --
Total Bill Paid (Rs) --
Coverage Vandazhy,vadakkenchery ,kizhakkenchery
Work Plan Download

Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Apr 2021 Package-1 Work in progress | 23% Completed | 29/04/2021 1.) 350mm DI pipe laid for a length of 4030.00m 2). column above plinth beam concrete work in progress. Package-II-PART-i Work in progress | 14% Completed | 29/04/2021 Vadakkencherry distribution network- (Vadakkenchery-thenidukke Road+ nayarthara road+anakkapara to thekupadam road+chinakkapadam to old NH road+old nh+diana side road +ridermain) 90mm 6kg 2952.00 m laid, 90mm 8 kg- 2991m laid and 160mm 8kg 102m laid. 80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 200 mm DI K9-390.50M AE3
28 Apr 2021 PHASE-II-package-I Work in progress | 23% Completed | 28/04/2021 1.) 350mm DI pipe laid for a length of 3400.00m 2). column above plinth beam shuttering and reinforcement work in progress. 2.) PHASE-II-Package-ii-part-I Work in progress | 14% Completed | 28/04/2021 Vadakkencherry distribution network- (Vadakkenchery-thenidukke Road+ nayarthara road+anakkapara to thekupadam road+chinakkapadam to old NH road+old nh+diana side road +ridermain) 90mm 6kg 2952.00 m laid, 90mm 8 kg- 2991m laid and 160mm 8kg 102m laid. 80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 200 mm DI K9-390.50M AE3
20 Apr 2021 Work in progress | 22% Completed | 20/04/2021 Plinth beam concrete work completed ,Casting of columns above plinth beam reinforcement work started and 350mm DI pipe laid for a length of 2716.50m AE3
17 Apr 2021 Work in progress | 22% Completed | 17/04/2021 350 mm DI pipe laid for a length of 2716.50 m AE3
13 Apr 2021 package-I Work in progress | 22% Completed | 13/04/2021 plinth beam concrete work in progress and pumping main 350 mm DI pipe laid for a length of 2418.00 m package-II-part-I Work in progress | 14% Completed | 13/04/2021 Vadakkencherry distribution network- Anakkappara- Mudappallur PWD Road: 90mm 6kg 990m laid, 90mm 8 kg-456m laid and 160mm 8kg 102m laid. vadakkanchery nayarthara road-90mm pvc 6 kg-132 m laid pulinkootam royal jn road-80 mm GI -107.70m laid 100mm GI-72.00m laid 125 mm GI-59.50m laid 150 mmGI -154.00M laid 90mm pvc 8 kg-1112m laid 110mm pvc-6 kg-1212.40 laid AE3

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Description Comments Issue Status
10 Feb 2021 Pending Pending Clearance from other department No comments available. Pending
09 Feb 2021 Pending Pending Package I - construction of 22 LL OHSR at Karimkunnam - The land for the constrution of OHSr belong sto private party. The WRD order and revenue order obtained for LA under LARR act 2013. The application submitted to District collector. The demand note for remitting contingency charge showing rough amount of acquisition as 5.88 crores received. Allotted amount for land acquisition is only one crore from KIIFB. Shortage of enough amount for completing the LA Procedure No comments available. Pending
09 Feb 2021 Pending Pending Clearance from other department No comments available. Pending

Packages

No. Project Name Location View
1 KIIFB – 2017-18 Vandazhi, Kizhakkenchery, Vadakkanchery and Kannambra Panchayaths in Palakkad District – phase II - package I - Design, construction,Commissioning and Maintenance of 22.00 LL OHSR at Karimkunnam in Vadakkanchery Panchayath, Supplying and Laying 350mm DI K9 CWPM from WTP to Karimkunnam OHSR, Supplying and Erection of ,CW motor pump sets including road restoration work Project Division Chittur
2 KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-III -Supplying and Laying distribution network in Low level zone of Vandazhy grama panchayath from 24.50 LL OHSR at Mangalam Dam WTP - Zone 1 Project Division Chittur
3 KIIFB-2017-2018-CWSS TO Vandazhy,Kizhakkenchery,vadakkenchery and kannambra panchayaths in palakkad district-Phase-II-Package-II-Part-I-Supplying laying testing commissioning and maintenance of distribution net work from 22 LL OHSR at Karimkunnam and Transmission main from OHSR up to Diana Hotel including NH 544 crossing for kannambra low level zone and road restoration Project Division Chittur
4 KIIFB 2017-2018-WSS to quality affected habitations of vandazhi, Kizhakkanchery and Vadakkanchery Gramapanchayath Phase II-Package-2-part-II Project Division Chittur

Duration & Sanction dates

Date of Sanction 19/11/2018
Date of start 13/03/2020
Expected date of Completion 04/11/2021

Other details

Project Officers View
Funding Agency KIIFB

Processing Dates

Administrative Sanction[AS] 19 Nov 2018
Technichal Sanction[TS] 13 Dec 2019
Estimate Approval 13 Dec 2019
NIT Approval 06 Mar 2020
Supplying and Laying 15 Jun 2020
Tender Closing 18 Jan 2020
Technichal Pre-Qualification 31 Jan 2020
Price bid opening 07 Feb 2020

Approval Dates

Head Office Approval 06 Jun 2020
Board Approval 18 Feb 2020
Final Approval 06 Mar 2020
Workorder Date 13 Mar 2020
Agreement Date 23 Mar 2020

Location