| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Mar 2026 | KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=489.5m,90/6kg=7368m,90/8kg=1278m,110/8kg=429m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6Kg=653m,80mm GI =156m | Chittur Project Dn - AE 3 | |
| 07 Mar 2026 | KIIFB phase II – package I (Work in progress 92% ) Contractor Styopped works and filed case agaist KWA ,waiting for court order. Present Progress -OHSR primer coat work completed and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14.742km laid. GAP filling work is balance ,crossing bridge work not started.MS pipe for crossing is supplied KIIFB phase II – package III (Work in progress 86% ) Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laid KIIFB phase II – package II-PART I (Work in progress 72% ) work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processing KIIFB phase II – package II-PART II (Work in progress 16% ) 200mmDI=489.5m,90/6kg=7242m,90/8kg=1278m,110/8kg=429m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6Kg=653m,80mm GI =156m | Chittur Project Dn - AE 3 | |
| 05 Mar 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=7158m,90/8kg=1278m,110/8kg=216m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m,80mm GI=48.4m | Chittur Project Dn - AE 3 | |
| 03 Mar 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=7158m,90/8kg=1278m,110/8kg=216m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m,80mm GI=48.4m | Chittur Project Dn - AE 3 | |
| 27 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=6834m,90/8kg=1278m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m,80mm GI=48.4m | Chittur Project Dn - AE 3 | |
| 25 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=6636m,90/8kg=1278m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m,80mm GI=26.7m | Chittur Project Dn - AE 3 | |
| 23 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=6368m,90/8kg=1146m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m | Chittur Project Dn - AE 3 | |
| 20 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=6020m,90/8kg=948m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2953.5m,160/6kg=653m | Chittur Project Dn - AE 3 | |
| 18 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=5504m,90/8kg=948m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2920.5m,160/6kg=653m | Chittur Project Dn - AE 3 | |
| 17 Feb 2026 | KIIFB PACKAGE II PHASE I 92% CompletedTOTAL PIPE LAID 6.618km laid/8 km pipe. House connections- 3377 Nos provided/out of 6055, FHTC: 79 Nos. 1.) 90mm PVC 6 kg -3.110 km laid 2) 80mm GI pipe- 3.508 Km laidKIIFB PACKAGE II PHASE III 86% Completed Various dia of pvc pipes and GI pipes are supplied at site Total supply-123 km, Total pipe laid – 113.53 km /123 km 1.) 90 mm 6 kg 49350 m supplied and 40912.35 m laid 2.) 90 mm 8 kg-37386 m supplied and 36910.50 m laid 3.) 90mm 10 kg – 240 m supplied and 240 m laid 4) 110mm 6 kg – 4278 m supplied and 4278 m laid 5) 110mm 8kg - 5268 m supplied and 4896 m laid 6) 140mm 6kg - 5620 m supplied 5542 m laid 7) 140mm 8 kg - 1953 m supplied and 1911 m laid 8) 160 mm 6 kg - 2928 m supplied and 2880 m laid 9) 160 mm 8 kg - 1050 m supplied 1014.50 m laid 10) 80 mm GI- 2580 m laid and 2067.30 m laid 11) 100 mm GI - 312 m supplied and 311.30 m laid 12) 125mm GI – 130 m supplied and 130 m laid 13) 150MM GI - 136.50 m supplied and 108.60 m laid 14) 450MM DI - 2189 m supplied and 2051.5 m laid 15) 200mm DI -1977.50 m supplied and 1977.50 m laid 16) 250mm DI -2915 m supplied and 2909.50 m laid 17) 400MM DI - 2833.00 m supplied and 2820.30 m laid 18) 350mm DI - 1772.5 m supplied and 1767 m 19) 300MM DI - 807 m supplied and 807 m laidKIIFB PHASE II PACKAGE II PART I 72% Completed work foreclosed -72% of work completed (1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , ) balance work arranged in kiifb ,its tender procedure processingKIIFB PHASE II PACKAGE II PART II 16% Completed 200mm DI=489.5m,90/6kg=5198m,90/8kg=948m,110/8kg=150m,110/6kg=1174m,140/6 kg=666m,250mm DI=181.5m,350mm DI=2920.5m,160/6kg=653m | Chittur Project Dn - AE 3 |