| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Jul 2023 | Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction | Kollam WS Sn 2 - AE | |
| 17 Jul 2023 | Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction | Kollam WS Sn 2 - AE | |
| 13 Jul 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 04 Jul 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 28 Jun 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 24 Jun 2023 | LOA issued, Pipe testing process under progress | Kollam WS Sn 2 - AE | |
| 20 Jun 2023 | AGREEMENT EXECUTED ON 20.06.23 | Kollam WS Sub Dn - AEE | |
| 20 Jun 2023 | LOA issued, Pipe testing process under progress | Kollam WS Sn 2 - AE |