Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work

Project DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Project Code KLMDEPO052314323
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Status Completed
District Kollam
Executing Office Kollam WS Sub Dn
AS Amount (Rs) 236000
AS Number 750918
TS Amount (Rs) 227000
TS Number WRD/KWA-CE(SR)/EST_TS/9112/2023_26_1_1
Total Bill Submitted (Rs) 154410
Total Bill Paid (Rs) 0
Population Benefitted 150
Capacity in MLD 1.00
Actual Project Completion Date 15 Jan 2024
Coverage DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-RWSS to Thrikkadavoor - Kollam Municipal Corporation - Extension of pipe line- Extension of pipe line near Anchalumoodu zonal office to Kunnadivayal road.-Pipeline Work Kollam WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2024 CC Ist & Final Bill submitted. ( E bill ) Kollam WS Sn 2 - AE
16 Jan 2024 Bill under preparation Kollam WS Sn 2 - AE
11 Jan 2024 Work completed. Kollam WS Sn 2 - AE
09 Jan 2024 Road crossing permission got and interconnection done. Kollam WS Sn 2 - AE
06 Jan 2024 Balance interconnection works will arrange today night 8 pm( heavy traficable area) Kollam WS Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/05/2023
Scheduled date of Completion of the Project 19 Jul 2023
Expected date of Completion 15/03/2024

Processing Dates

AS Date 08 May 2023
TS Date 12 May 2023

Other details

Project Officers View