| 08 Feb 2024 | CC Ist & Final Bill submitted. ( E bill ) | Kollam WS Sn 2 - AE | |
| 16 Jan 2024 | Bill under preparation | Kollam WS Sn 2 - AE | |
| 11 Jan 2024 | Work completed. | Kollam WS Sn 2 - AE | |
| 09 Jan 2024 | Road crossing permission got and interconnection done. | Kollam WS Sn 2 - AE | |
| 06 Jan 2024 | Balance interconnection works will arrange today night 8 pm( heavy traficable area) | Kollam WS Sn 2 - AE | |
| 03 Jan 2024 | Agreement executing by NH PWD Road subdivision under process. | Kollam WS Sn 2 - AE | |
| 29 Dec 2023 | Agreement executing by NH authorities for getting tar cutting sanction under process. Request for time of extension submitted. | Kollam WS Sn 2 - AE | |
| 26 Dec 2023 | Agreement executing by NH authorities for getting tar cutting sanction under process | Kollam WS Sn 2 - AE | |
| 22 Dec 2023 | As per demand notice estimate amount & supervision charge remitted. Agreement executing pending. | Kollam WS Sn 2 - AE | |
| 19 Dec 2023 | Demand notice from NH Dept. got and submitted to higher office for fund request. | Kollam WS Sn 2 - AE |