Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Feb 2024 CC Ist & Final Bill submitted. ( E bill ) Kollam WS Sn 2 - AE
16 Jan 2024 Bill under preparation Kollam WS Sn 2 - AE
11 Jan 2024 Work completed. Kollam WS Sn 2 - AE
09 Jan 2024 Road crossing permission got and interconnection done. Kollam WS Sn 2 - AE
06 Jan 2024 Balance interconnection works will arrange today night 8 pm( heavy traficable area) Kollam WS Sn 2 - AE
03 Jan 2024 Agreement executing by NH PWD Road subdivision under process. Kollam WS Sn 2 - AE
29 Dec 2023 Agreement executing by NH authorities for getting tar cutting sanction under process. Request for time of extension submitted. Kollam WS Sn 2 - AE
26 Dec 2023 Agreement executing by NH authorities for getting tar cutting sanction under process Kollam WS Sn 2 - AE
22 Dec 2023 As per demand notice estimate amount & supervision charge remitted. Agreement executing pending. Kollam WS Sn 2 - AE
19 Dec 2023 Demand notice from NH Dept. got and submitted to higher office for fund request. Kollam WS Sn 2 - AE