Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Sep 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. Kollam WS Sn 2 - AE
01 Sep 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. Kollam WS Sn 2 - AE
24 Aug 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. Kollam WS Sn 2 - AE
18 Aug 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. Kollam WS Sn 2 - AE
15 Aug 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor Kollam WS Sn 2 - AE
11 Aug 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor Kollam WS Sn 2 - AE
02 Aug 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor Kollam WS Sn 2 - AE
29 Jul 2023 Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Kollam WS Sn 2 - AE
27 Jul 2023 Pipe laying work completed and interconnection work pending due to delay for getting road cutting sanction Kollam WS Sn 2 - AE
24 Jul 2023 Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction Kollam WS Sn 2 - AE