| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 01 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 24 Aug 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 18 Aug 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 15 Aug 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor | Kollam WS Sn 2 - AE | |
| 11 Aug 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor | Kollam WS Sn 2 - AE | |
| 02 Aug 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted by the contractor | Kollam WS Sn 2 - AE | |
| 29 Jul 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. | Kollam WS Sn 2 - AE | |
| 27 Jul 2023 | Pipe laying work completed and interconnection work pending due to delay for getting road cutting sanction | Kollam WS Sn 2 - AE | |
| 24 Jul 2023 | Work started on 14/7/2023 interconnection work pending due to delay for getting road cutting sanction | Kollam WS Sn 2 - AE |