| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Nov 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 25 Oct 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 16 Oct 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 09 Oct 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 03 Oct 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 25 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. This matter already informed to Hon'ble MLA. | Kollam WS Sn 2 - AE | |
| 21 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 18 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 12 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE | |
| 08 Sep 2023 | Pipe laying work completed. Delay for completion is not getting sanction from Tar crossing. Applied to Row portal on 8/6/23, but demand notice not submitted. Request for time of extension submitted to higher office. | Kollam WS Sn 2 - AE |