Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Mar 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
27 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
24 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
21 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
18 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
15 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
12 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1127Nos out of 2150 Nos completed, first and final bill under preparation | Kannur WS Sn AE 2 | |
06 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1118Nos out of 2150 Nos completed, Road restoration work in progress | Kannur WS Sn AE 2 | |
03 Feb 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1118Nos out of 2150 Nos completed, Road restoration work in progress | Kannur WS Sn AE 2 | |
31 Jan 2025 | Pipe laid 2300 m out of 2300 m and FHTC 1100 Nos out of 2150 Nos completed, Road restoration work in progress | Kannur WS Sn AE 2 |