AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work
AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work
Project Code
KNRAMRUT 2112417607
Type
Main project
Funding Agency
AMRUT 2
Category
AMRUT 2
Type of scheme
Water Supply
Scheme
Description
AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work.
Status
On-going
District
Kannur
Executing Office
Thaliparambu WS Dn
AS Amount (Rs)
45000000
AS Number
G.O.(Rt)No.2263/2024/LSGD
TS Amount (Rs)
44100000
TS Number
147/2025-2026
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work
Thaliparamba WS Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
28 Sep 2026
Tank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given.
Thaliparamba WS Section
02 Jul 2026
Tank top slab work completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 600 connections given.
Thaliparamba WS Section
25 Jun 2026
Tank top slab work completed. Handrails work and vertical pipe works going on. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.
Thaliparamba WS Section
09 Jun 2026
Tank top slab work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given.
Thaliparamba WS Section
12 May 2026
Tank wall up to top slab completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 225 connections given.