| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2026 | Tank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given. | Thaliparamba WS Section | |
| 02 Jul 2026 | Tank top slab work completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 600 connections given. | Thaliparamba WS Section | |
| 25 Jun 2026 | Tank top slab work completed. Handrails work and vertical pipe works going on. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given. | Thaliparamba WS Section | |
| 09 Jun 2026 | Tank top slab work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given. | Thaliparamba WS Section | |
| 12 May 2026 | Tank wall up to top slab completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 225 connections given. | Thaliparamba WS Section | |
| 24 Apr 2026 | Tank wall up to 1.8m completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. | Thaliparamba WS Section | |
| 07 Apr 2026 | Deck beam concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. | Thaliparamba WS Section | |
| 27 Mar 2026 | Deck beam concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. | Thaliparamba WS Section | |
| 13 Mar 2026 | Deck beam concrete work completed. PVC pipe laid for 2.3km. DI pipe laying started. 120 connections given. | Thaliparamba WS Section | |
| 04 Mar 2026 | Deck beam reinforcement work completed. PVC pipe laid for 2.3km. DI pipe laying started. | Thaliparamba WS Section |