Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Sep 2026 Tank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given. Thaliparamba WS Section
02 Jul 2026 Tank top slab work completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 600 connections given. Thaliparamba WS Section
25 Jun 2026 Tank top slab work completed. Handrails work and vertical pipe works going on. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given. Thaliparamba WS Section
09 Jun 2026 Tank top slab work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given. Thaliparamba WS Section
12 May 2026 Tank wall up to top slab completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 225 connections given. Thaliparamba WS Section
24 Apr 2026 Tank wall up to 1.8m completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. Thaliparamba WS Section
07 Apr 2026 Deck beam concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. Thaliparamba WS Section
27 Mar 2026 Deck beam concrete work completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 160 connections given. Thaliparamba WS Section
13 Mar 2026 Deck beam concrete work completed. PVC pipe laid for 2.3km. DI pipe laying started. 120 connections given. Thaliparamba WS Section
04 Mar 2026 Deck beam reinforcement work completed. PVC pipe laid for 2.3km. DI pipe laying started. Thaliparamba WS Section