| Project | AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work |
|---|---|
| Project Code | KNRAMRUT 2112417607P1 |
| Type | Package |
| Main Project | AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work |
| Funding Agency | AMRUT 2 |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | |
| Description | AMRUT-2.0 - TALIPARAMBA MUNCIPALITY-BALANCE WORK- CONSTRUCTION OF 1 LAKH LITRE OHSR AT VATTAPARA, LAYING TRANSMISION MAIN, DISTRIBUTION PIPE LINE AND PROVIDING FHTCs-Pipeline Work. |
| Status | On-going |
| District | Kannur |
| Executing Office | Thaliparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 44100000 |
| TS Number | 147/2025-2026 |
| Technical specification | |
| Contractor | M/s SRPT Engineering Pvt Ltd (Mob: 9745451741) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | Date is not specified |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| TS Date | 06 Apr 2025 |
|---|---|
| Estimate Approval | 11 Mar 2025 |
| NIT Approval | 06 Apr 2025 |
| Thaliparamba WS Section |
| Date: 28/09/2026 |
Work in progress | 75% Completed
ank structure completed. Handrails work and vertical pipe works completed. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 780 connections given..
| Thaliparamba WS Section |
| Date: 02/07/2026 |
Work in progress | 65% Completed
Tank top slab work completed. vertical pipe work and handrail work started. PVC pipe laid for 5.7km. DI pipe laid for 1.1km. 345 connections given..