Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work

Project Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work
Project Code PKDJJM09219403P2
Type Package
Main Project JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work
Status On-going
District Palakkad
Executing Office Shoranur Sn
Agreement Number
Agreement Date
TS Amount (Rs) 9036181
TS Number WRD/KWA-CE(NR)/EST_TS/13080/2023_26_1_1
Technical specification In this Estimate 90mm HDPE  is recasted to 2102m and 80mm GI recasted to 5168 m

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/07/2023
Scheduled date of Completion as per agreement 09 Aug 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 09 Jun 2023
Estimate Approval 09 Jun 2023
Tender Closing 22 Jun 2023
Technichal Pre-Qualification 22 Jun 2023
Price bid opening 23 Jun 2023

Approval Dates

Workorder Date 22 Jun 2023
NA 10 Jul 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Shoranur PH Sn AE
Date: 25/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m.

Shoranur PH Sn AE
Date: 22/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m.