Project | Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work |
---|---|
Project Code | PKDJJM09219403P2 |
Type | Package |
Main Project | JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work |
Status | On-going |
District | Palakkad |
Executing Office | Shoranur Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 9036181 |
TS Number | WRD/KWA-CE(NR)/EST_TS/13080/2023_26_1_1 |
Technical specification | In this Estimate 90mm HDPE is recasted to 2102m and 80mm GI recasted to 5168 m |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/07/2023 |
---|---|
Scheduled date of Completion as per agreement | 09 Aug 2023 |
Expected date of Completion | 31/07/2024 |
TS Date | 09 Jun 2023 |
---|---|
Estimate Approval | 09 Jun 2023 |
Tender Closing | 22 Jun 2023 |
Technichal Pre-Qualification | 22 Jun 2023 |
Price bid opening | 23 Jun 2023 |
Workorder Date | 22 Jun 2023 |
---|---|
NA | 10 Jul 2023 |
Shoranur PH Sn AE |
Date: 25/06/2024 |
Work in progress | 71% Completed
80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m.
Shoranur PH Sn AE |
Date: 22/06/2024 |
Work in progress | 71% Completed
80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m.