Shoranur PH Sn AE
Date: 01/07/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 25/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 22/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 20/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 17/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 12/06/2024

Work in progress | 71% Completed

80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m

Shoranur PH Sn AE
Date: 09/06/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 06/06/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 02/06/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 26/05/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 20/05/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 08/05/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 04/05/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 28/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 21/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 17/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 14/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 10/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 05/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 02/04/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 30/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 26/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 22/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 17/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 10/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 02/03/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 25/02/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 24/02/2024

Work in progress | 70% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m

Shoranur PH Sn AE
Date: 19/02/2024

Work in progress | 62% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 1500m

Shoranur PH Sn AE
Date: 12/02/2024

Work in progress | 62% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 1500m

Shoranur PH Sn AE
Date: 08/02/2024

Work in progress | 59% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 1500m

Shoranur PH Sn AE
Date: 07/02/2024

Work in progress | 58% Completed

80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 1500m

Shoranur PH Sn AE
Date: 01/02/2024

Work in progress | 38% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1300m

Shoranur PH Sn AE
Date: 29/01/2024

Work in progress | 38% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1300m

Shoranur PH Sn AE
Date: 25/01/2024

Work in progress | 37% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1300m

Shoranur PH Sn AE
Date: 22/01/2024

Work in progress | 35% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1000m.

Shoranur PH Sn AE
Date: 19/01/2024

Work in progress | 35% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1000m.

Shoranur PH Sn AE
Date: 18/01/2024

Work in progress | 35% Completed

80mm GI Pipe laid = 2400m, 90mm HDPE Pipe laid = 1000m.

Shoranur PH Sn AE
Date: 16/01/2024

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 11/01/2024

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 08/01/2024

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 05/01/2024

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 29/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 26/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 22/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 19/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 16/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 14/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 11/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 08/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 05/12/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 30/11/2023

Work in progress | 20% Completed

Work in progress

Shoranur PH Sn AE
Date: 27/11/2023

Work in progress | 14% Completed

Work in progress

Shoranur PH Sn AE
Date: 24/11/2023

Work in progress | 14% Completed

Work in progress

Shoranur PH Sn AE
Date: 20/11/2023

Work in progress | 14% Completed

Work in progress

Shoranur PH Sn AE
Date: 16/11/2023

Work in progress | 14% Completed

Work in progress

Shoranur PH Sn AE
Date: 13/11/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 10/11/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 07/11/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 03/11/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 01/11/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 25/10/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 19/10/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 16/10/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 10/10/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 03/10/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 29/09/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 25/09/2023

Work in progress | 12% Completed

Work in progress

Shoranur PH Sn AE
Date: 18/09/2023

Work in progress | 10% Completed

Work in progress

Shoranur PH Sn AE
Date: 11/09/2023

Work in progress | 10% Completed

Work in progress

Shornur PH Dn EE
Date: 05/09/2023

Work in progress | 10% Completed

Work in progress.Agreement executed.