Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II

Project JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II
Project Code PKDJJM09219403
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II
Status On-going
District Palakkad
Executing Office Shornur PH Dn
AS Amount (Rs) 130500000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 94200000
TS Number TS/2021-2022/2021/1031
Total Bill Submitted (Rs) 84664355
Total Bill Paid (Rs) 84664355
Population Benefitted 31337
Capacity in MLD 8.00
Actual Project Completion Date Date is not specified
Coverage 2532nos
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Additional Pipe laying works in Kappur Grama Panchayath-Pipeline Work-Pipeline Work Shoranur Sn
2 JJM 2020 - 21 -Supplying, laying, testing, commissioning and mace of distribution system and providing FHTCs (2532nos) in Kappur Panchayath- Phase II Shoranur Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jun 2024 Additional work80mm GI Pipe laid = 2600m, 90mm HDPE Pipe laid = 2152m,90 mm PE Pipe - 24000 m laid, 110 mm PE Pipe - 3000 m laid, 140mm-2010m, 160mm - 3960, 80mm GI -4293 laid, FHTCs given - 2133nos, HTCs - 8nos. Shoranur PH Sn AE
09 Jun 2024 Additional work -80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m 90 mm PE Pipe - 24000 m laid, 110 mm PE Pipe - 3000 m laid, 140mm-2010m, 160mm - 3960, 80mm GI -4293 laid, FHTCs given - 2121nos, HTCs - 15nos Shoranur PH Sn AE
06 Jun 2024 Additional work -80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m 90 mm PE Pipe - 24000 m laid, 110 mm PE Pipe - 3000 m laid, 140mm-2010m, 160mm - 3960, 80mm GI -4293 laid, FHTCs given - 2121nos, HTCs - 15nos Shoranur PH Sn AE
02 Jun 2024 Additional work -80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m 90 mm PE Pipe - 24000 m laid, 110 mm PE Pipe - 3000 m laid, 140mm-2010m, 160mm - 3960, 80mm GI -4293 laid, FHTCs given - 2121nos, HTCs - 15nos Shoranur PH Sn AE
26 May 2024 Additional work -80mm GI Pipe laid = 2500m, 90mm HDPE Pipe laid = 2102m 90 mm PE Pipe - 24000 m laid, 110 mm PE Pipe - 3000 m laid, 140mm-2010m, 160mm - 3960, 80mm GI -4293 laid, FHTCs given - 2121nos, HTCs - 15nos Shoranur PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 09/02/2022
Scheduled date of Completion of the Project 08 Aug 2022
Expected date of Completion 30/01/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 24 Nov 2021

Other details

Project Officers View