| Project | AMRUT-1.0-Kozhikode Water Supply Project-Providing FHTCs by Extension of pipe line in Ward 08-Pipeline Work |
|---|---|
| Project Code | CLTAMRUT032313801P38 |
| Type | Package |
| Main Project | AMRUT 1.0-Kozhikode Water Supply Project-Providing FHTCs and Pipe Line extension |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT-1.0-Kozhikode Water Supply Project-Providing FHTCs by Extension of pipe line in Ward 08-Pipeline Work |
| Status | On-going |
| District | Kozhikkode |
| Executing Office | Kozhikode Dist 2 Sn 2 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 14000000 |
| TS Number | 11451/2023-2024 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 09/10/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 17 Apr 2024 |
| Expected date of Completion | 31/05/2024 |
| TS Date | 08 Aug 2023 |
|---|---|
| Estimate Approval | 04 Aug 2023 |
| Workorder Date | 08 Sep 2023 |
|---|---|
| NA | 23 Sep 2023 |
| Kozhikode PH Dn EE |
| Date: 31/05/2024 |
Work has been completed | 100% Completed
Work completed. Pipe laid-2050m, FHTCs-476 nos..
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 85% Completed
Work In Progress.