Kozhikode PH Dn EE
Date: 31/05/2024

Work has been completed | 100% Completed

Work completed. Pipe laid-2050m, FHTCs-476 nos.

Kozhikode PH Dn EE
Date: 20/04/2024

Work in progress | 85% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 04/04/2024

Work in progress | 66% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 12/03/2024

Work in progress | 60% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 05/03/2024

Work in progress | 54% Completed

pipe laid 2.05km, FHTCs-295 nos.

Kozhikode PH Dn EE
Date: 04/03/2024

Work in progress | 51% Completed

pipe laid 2.05km, FHTCs-295 nos.

Kozhikode PH Dn EE
Date: 03/03/2024

Work in progress | 50% Completed

pipe laid 2.05km, FHTCs-295 nos.

Kozhikode PH Dn EE
Date: 02/03/2024

Work in progress | 49% Completed

pipe laid 2.05km, FHTCs-295 nos.

Kozhikode PH Dn EE
Date: 01/03/2024

Work in progress | 48% Completed

pipe laid 2.05km, FHTCs-295 nos.

Kozhikode PH Dn EE
Date: 14/02/2024

Work in progress | 45% Completed

Work In Progress

Kozhikode PH Dn EE
Date: 30/01/2024

Work in progress | 42% Completed

Work in progress

Kozhikode PH Dn EE
Date: 29/01/2024

Work in progress | 41% Completed

Work in progress

Kozhikode PH Dn EE
Date: 27/01/2024

Work in progress | 40% Completed

Work in progress

Kozhikode PH Dn EE
Date: 08/01/2024

Work in progress | 34% Completed

pipe laid-1028m. Work in progress

Kozhikode PH Dn EE
Date: 07/01/2024

Work in progress | 31% Completed

pipe laid-1028m. Work in progress

Kozhikode PH Dn EE
Date: 06/01/2024

Work in progress | 29% Completed

pipe laid-1028m. Work in progress

Kozhikode PH Dn EE
Date: 05/01/2024

Work in progress | 24% Completed

pipe laid-1028m. Connection Work in progress

Kozhikode PH Dn EE
Date: 04/01/2024

Work in progress | 23% Completed

pipe laid-1028m. Connection Work in progress

Kozhikode PH Dn EE
Date: 03/01/2024

Work in progress | 23% Completed

pipe laid-1028m. Connection Work in progress

Kozhikode PH Dn EE
Date: 02/01/2024

Work in progress | 23% Completed

pipe laid-1028m. Connection Work in progress

Kozhikode PH Dn EE
Date: 01/01/2024

Work in progress | 22% Completed

pipe laid-1028m. Connection Work in progress

Kozhikode PH Dn EE
Date: 11/12/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 28/11/2023

Work has started | 0% Completed

Agreement Executed

Kozhikode PH Dn EE
Date: 20/11/2023

Work has started | 0% Completed

Site handed over to the contractor

Kozhikode PH Dn EE
Date: 28/10/2023

Work has started | 0% Completed

Site Handed Over