| Kozhikode PH Dn EE |
| Date: 31/05/2024 |
Work has been completed | 100% Completed
Work completed. Pipe laid-2050m, FHTCs-476 nos.
| Kozhikode PH Dn EE |
| Date: 20/04/2024 |
Work in progress | 85% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 04/04/2024 |
Work in progress | 66% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 12/03/2024 |
Work in progress | 60% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 05/03/2024 |
Work in progress | 54% Completed
pipe laid 2.05km, FHTCs-295 nos.
| Kozhikode PH Dn EE |
| Date: 04/03/2024 |
Work in progress | 51% Completed
pipe laid 2.05km, FHTCs-295 nos.
| Kozhikode PH Dn EE |
| Date: 03/03/2024 |
Work in progress | 50% Completed
pipe laid 2.05km, FHTCs-295 nos.
| Kozhikode PH Dn EE |
| Date: 02/03/2024 |
Work in progress | 49% Completed
pipe laid 2.05km, FHTCs-295 nos.
| Kozhikode PH Dn EE |
| Date: 01/03/2024 |
Work in progress | 48% Completed
pipe laid 2.05km, FHTCs-295 nos.
| Kozhikode PH Dn EE |
| Date: 14/02/2024 |
Work in progress | 45% Completed
Work In Progress
| Kozhikode PH Dn EE |
| Date: 30/01/2024 |
Work in progress | 42% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 29/01/2024 |
Work in progress | 41% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 27/01/2024 |
Work in progress | 40% Completed
Work in progress
| Kozhikode PH Dn EE |
| Date: 08/01/2024 |
Work in progress | 34% Completed
pipe laid-1028m. Work in progress
| Kozhikode PH Dn EE |
| Date: 07/01/2024 |
Work in progress | 31% Completed
pipe laid-1028m. Work in progress
| Kozhikode PH Dn EE |
| Date: 06/01/2024 |
Work in progress | 29% Completed
pipe laid-1028m. Work in progress
| Kozhikode PH Dn EE |
| Date: 05/01/2024 |
Work in progress | 24% Completed
pipe laid-1028m. Connection Work in progress
| Kozhikode PH Dn EE |
| Date: 04/01/2024 |
Work in progress | 23% Completed
pipe laid-1028m. Connection Work in progress
| Kozhikode PH Dn EE |
| Date: 03/01/2024 |
Work in progress | 23% Completed
pipe laid-1028m. Connection Work in progress
| Kozhikode PH Dn EE |
| Date: 02/01/2024 |
Work in progress | 23% Completed
pipe laid-1028m. Connection Work in progress
| Kozhikode PH Dn EE |
| Date: 01/01/2024 |
Work in progress | 22% Completed
pipe laid-1028m. Connection Work in progress
| Kozhikode PH Dn EE |
| Date: 11/12/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 28/11/2023 |
Work has started | 0% Completed
Agreement Executed
| Kozhikode PH Dn EE |
| Date: 20/11/2023 |
Work has started | 0% Completed
Site handed over to the contractor
| Kozhikode PH Dn EE |
| Date: 28/10/2023 |
Work has started | 0% Completed
Site Handed Over