JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and Low Level zone and providing House connections in Tanalur GP in Malappuram District-
Project |
JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and Low Level zone and providing House connections in Tanalur GP in Malappuram District- |
Project Code |
MLPJJM09219417 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying Distribution networks and FHTCs |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram Project Dn |
AS Amount (Rs) |
681700000
|
AS Number |
G.O(Rt) No.489/2021/WRD |
TS Amount (Rs) |
314900000 |
TS Number |
14919/2021-2022 |
Total Bill Submitted (Rs) |
75555624 |
Total Bill Paid (Rs) |
75555624 |
Population Benefitted |
75353 |
Capacity in MLD |
7.54 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Package - 1 -JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and providing House connections in Tanalur GP in Malappuram District- |
Project Division Malappuram |
|
2 |
Package - 2 JJM - WSS to Tanalur Grama Panchayath in Malappuram District Part-2 - Supply and Laying of Distribution Network and Providing FHTC at Low level Zone |
Project Division Malappuram |
|
3 |
Package 3 - Jal Jeevan Mission (JJM) - WSS To Tanur Muncipality and adjoining four panchayaths in Malappuram District - PWD Road Restoration (BM&BC) In Tanalur GP |
Project Division Malappuram |
|
4 |
Package 4 - Jal Jeevan Mission (JJM) - WSS To Tanur Muncipality and adjoining four panchayaths in Malappuram District - LSGD Road Restoration (BT) In Tanalur GP |
Project Division Malappuram |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Sep 2023 |
In package 1, 55%- Pipe laying and connection works in progress. Package 2, 31%- Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
03 Aug 2023 |
In package 1, 53% - Pipe laying and connection works in progress. Package 2, 29% - Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
22 Jul 2023 |
In package 1, 53% - Pipe laying and connection works in progress. Package 2, 28% - Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
30 Jun 2023 |
In package 1, 51%- Pipe laying and connections work in progress. Package 2, 25%- Pipe laying and connection work in progress.
|
Malappuram Project Dn AE5 |
|
01 Jun 2023 |
In package 1, 49%- Pipe laying and connections work in progress. Package 2, 20%- Pipe laying and connection work in progress.
|
Malappuram Project Dn AE5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/03/2022 |
Scheduled date of Completion of the Project |
14 Dec 2022 |
Expected date of Completion |
01/03/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
07 Dec 2021 |