Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Sep 2023 |
In package 1, 55%- Pipe laying and connection works in progress. Package 2, 31%- Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
03 Aug 2023 |
In package 1, 53% - Pipe laying and connection works in progress. Package 2, 29% - Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
22 Jul 2023 |
In package 1, 53% - Pipe laying and connection works in progress. Package 2, 28% - Work stopped due to heavy rain.
|
Malappuram Project Dn AE5 |
|
30 Jun 2023 |
In package 1, 51%- Pipe laying and connections work in progress. Package 2, 25%- Pipe laying and connection work in progress.
|
Malappuram Project Dn AE5 |
|
01 Jun 2023 |
In package 1, 49%- Pipe laying and connections work in progress. Package 2, 20%- Pipe laying and connection work in progress.
|
Malappuram Project Dn AE5 |
|
03 May 2023 |
In package 1, 47%- Pipe laying and connections work in progress. In package 2, 15%- Pipe laying and connections work in progress
|
Malappuram Project Dn AE5 |
|
18 Apr 2023 |
In package 1, 46%- Pipe laying and connections work in progress. Package 2, 14%- Pipe laying and connections work in progress. |
Malappuram Project Dn AE5 |
|
01 Apr 2023 |
In package 1, 45%- Pipe laying and connections work in progress. Package 2, 12%- Pipe laying and connections work in progress. |
Malappuram Project Dn AE5 |
|
14 Mar 2023 |
In package 1, 45%- Pipe laying and connections work in progress. In package 2, 10%- Pipe laying and connections work in progress.
|
Malappuram Project Dn AE5 |
|
24 Feb 2023 |
In package 1, 43%- PE Pipe laying work and connections work in progress. In package 2, 7%- PE Pipe laying work and connections work in progress. |
Malappuram Project Dn AE5 |
|