Package - 1 -JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and providing House connections in Tanalur GP in Malappuram District-

Project Package - 1 -JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and providing House connections in Tanalur GP in Malappuram District-
Project Code MLPJJM09219417P1
Type Package
Main Project JJM -Tanalur GP - WSS to Tanur MUnicipality and Adjoining 4 Gps - Phase - II - Laying Distribution network for High Level Zone and Low Level zone and providing House connections in Tanalur GP in Malappuram District-
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying Disrtribution net work and Providing FHTCs
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 314900000
TS Number 14919/2021-2022
Technical specification 147.9 KM Distribution Networks and 5420 FHTCs

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 30/03/2022
Scheduled date of Completion as per agreement 31 May 2023
Expected date of Completion 31/05/2023

Processing Dates

TS Date 07 Dec 2021
Estimate Approval 07 Dec 2021
NIT Approval 17 Dec 2021
Tender Closing 03 Jan 2022
Technichal Pre-Qualification 19 Jan 2022
Price bid opening 20 Jan 2022

Approval Dates

Workorder Date 15 Feb 2022
NA 24 Feb 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE5
Date: 26/06/2024

Work in progress | 57% Completed

Pipe laying and connection Work in progress. .

Malappuram Project Dn AE5
Date: 25/06/2024

Work in progress | 57% Completed

Pipe laying and connection Work in progress. .