JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households
Project |
JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
Project Code |
TVMJJM08207555 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Neyyattinkara WS Dn |
AS Amount (Rs) |
17600000
|
AS Number |
541/2020/WRD |
TS Amount (Rs) |
12800000 |
TS Number |
TS/2020-21/2020/14521 |
Total Bill Submitted (Rs) |
4981962 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
3800 |
Capacity in MLD |
3.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Perumkadavila panchayath area |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
Parassala WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Jun 2022 |
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS |
Neyyattinkara WS Dn EE |
|
27 Apr 2022 |
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS |
Neyyattinkara WS Dn EE |
|
05 Apr 2022 |
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS |
Neyyattinkara WS Dn EE |
|
02 Apr 2022 |
Work has been completed | 100% Completed | 02/04/2022
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS |
Neyyattinkara WS Dn EE |
|
25 Mar 2022 |
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS |
Neyyattinkara WS Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/12/2020 |
Scheduled date of Completion of the Project |
16 Jun 2021 |
Expected date of Completion |
30/09/2021 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
04 Sep 2020 |