Project | JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
---|---|
Project Code | TVMJJM08207555P1 |
Type | Package |
Main Project | JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-2020-2021 Perumkadavila Panchayath Part 2 RWSS to Marayamuttam and Kodithookimala water supply line extension and Providing water connections from existing and proposed pipeline to households |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Parassala WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 12800000 |
TS Number | TS/2020-21/2020/14521 |
Technical specification | . Providing and laying 20mm uPVC pipe is proposed to provide connections of more than 5.00 meter in length. Provision for road restoration charges is also included for house connections and pipe line extensions in PWD roads. Also provision for control valves, air valves and valve chambers are given in required stretches. Provision for plain cement concrete is given for restoration of tar/concrete cut areas |
Contractor | AJI A (Mob: 9995213765) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 17/12/2020 |
---|---|
Scheduled date of Completion as per agreement | 01 Jun 2021 |
Expected date of Completion | 30/06/2021 |
TS Date | 04 Sep 2020 |
---|---|
Estimate Approval | 04 Sep 2020 |
NIT Approval | 04 Sep 2020 |
Tender Closing | 03 Nov 2020 |
Price bid opening | 17 Dec 2020 |
Workorder Date | 17 Dec 2020 |
---|---|
NA | 12 Jan 2021 |
Parassala WS Sn |
Date: 25/07/2022 |
Work has been completed | 100% Completed
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS.
Parassala WS Sn |
Date: 24/07/2022 |
Work has been completed | 100% Completed
1083/950FHTC COMPLETED WORK HAD COMPLETED AND FINAL BILL SUBMITTED.EXCESS CONNECTION IS DUE TO THE REQUEST FROM PANCHAYATH MEMBERS AND CONSUMERS.