Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III-

Project Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III-
Project Code TCRJJM022213950
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III-
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 422000000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 10000000
TS Number WRD/KWA-CE(CR)/EST_TS/5973/2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 6290
Capacity in MLD 33.00
Actual Project Completion Date Date is not specified
Coverage Punnayur Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Grama Panchayath -Phase-III-Part-2-Pipeline Work Kunnamkulam Sn
2 Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III-Part-1-General Civil Work Kunnamkulam Sn
3 Jal Jeevan Mission (JJM)-Augmentation of PRWSS Providing Pipeline -in Punayyur Panchayath Phase III Part VI-General Civil Work Kunnamkulam Sn
4 Jal Jeevan Mission (JJM)-Augmentation of PRWSS Providing Pipeline-in Punnayur panchayath Phase III Part VII-General Civil Work Kunnamkulam Sn
5 Jal Jeevan Mission (JJM)-Augmentation of PRWSS Providing Pipeline in Punnayur Panchayath -Phase III-Part VI-Road restoration works-General Civil Work Kunnamkulam Sn
6 Jal Jeevan Mission (JJM)-Augmentation of PRWSS-PWD & LSGD Road Restoration Work-Punnayur Panchayath Phase III Part XI General Civil Work Kunnamkulam Sn
7 Jal Jeevan Mission (JJM)-Augmentation of PRWSS -PWD Road Restoration -Punnayur Panchayath Phase III-Part IX-General Civil Work Kunnamkulam Sn
8 Jal Jeevan Mission (JJM)-Augmentation of PRWSS-PWD Road Restoration Work-in Punnayur Panchayath Phase III Part X General Civil Work Kunnamkulam Sn
9 Jal Jeevan Mission (JJM)- Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCS-in Punnayur Panchayath - Phase III-Part VIII-Road Restoration Works PWD in Punnayur Panchayath-General Civil Work Kunnamkulam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 Work Order issued. Agreement executed . Part 1-Work Ongoing 206 FHTCs given.Part 2 -Final bill submitted .437 FHTCs given. Other packages work ongoing Kunnamkulam PH Sn - AE
24 Jun 2024 Work Order issued. Agreement executed . Part 1-Work Ongoing 206 FHTCs given.Part 2 -Final bill submitted .437 FHTCs given. Other packages work ongoing Kunnamkulam PH Sn - AE
22 Jun 2024 Work Order issued. Agreement executed . Part 1-Work Ongoing 206 FHTCs given.Part 2 -Final bill submitted .437 FHTCs given. Other packages work ongoing Kunnamkulam PH Sn - AE
20 Jun 2024 Work Order issued. Agreement executed . Part 1-Work Ongoing 206 FHTCs given.Part 2 -Final bill submitted .437 FHTCs given. Other packages work ongoing Kunnamkulam PH Sn - AE
19 Jun 2024 Work Order issued. Agreement executed . Part 1-Work Ongoing 206 FHTCs given.Part 2 -Final bill submitted .437 FHTCs given. Other packages work ongoing Kunnamkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/03/2023
Scheduled date of Completion of the Project 03 Aug 2023
Expected date of Completion 12/08/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 17 Mar 2023

Other details