Project | Jal Jeevan Mission (JJM)-Augmentation of PRWSS-PWD Road Restoration Work-in Punnayur Panchayath Phase III Part X General Civil Work |
---|---|
Project Code | TCRJJM022213950P6 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III- |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission (JJM)-Augmentation of PRWSS-PWD Road Restoration Work-in Punnayur Panchayath Phase III Part X General Civil Work |
Status | On-going |
District | Thrissur |
Executing Office | Kunnamkulam Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 10000000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/18722/2023_5_1_1 Dated: 02-08-2023 |
Technical specification | PWD Road Restoration Work-in Punnayur Panchayath Phase III Part X General Civil Work |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 16/08/2023 |
---|---|
Scheduled date of Completion as per agreement | 15 Nov 2023 |
Expected date of Completion | 31/07/2024 |
TS Date | 02 Aug 2023 |
---|---|
Estimate Approval | 02 Aug 2023 |
NIT Approval | 02 Aug 2023 |
Tender Closing | 09 Aug 2023 |
Technichal Pre-Qualification | 09 Aug 2023 |
Price bid opening | 10 Aug 2023 |
Workorder Date | 16 Aug 2023 |
---|---|
NA | 08 Sep 2023 |
Kunnamkulam PH Sn - AE |
Date: 28/06/2024 |
Work has started | 0% Completed
Work order issued on 16/08/2023. Agreement executed on 08.09.2023 .
Kunnamkulam PH Sn - AE |
Date: 27/06/2024 |
Work has started | 0% Completed
Work order issued on 16/08/2023. Agreement executed on 08.09.2023 .