Jal Jeevan Mission (JJM)-Augmentation of PRWSS -PWD Road Restoration -Punnayur Panchayath Phase III-Part IX-General Civil Work

Project Jal Jeevan Mission (JJM)-Augmentation of PRWSS -PWD Road Restoration -Punnayur Panchayath Phase III-Part IX-General Civil Work
Project Code TCRJJM022213950P5
Type Package
Main Project Jal Jeevan Mission (JJM)-2022-23-Augmentation of PRWSS Providing FHTCs -in Punnayur Panchayath-Phase-III-
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Augmentation of PRWSS -PWD Road Restoration -Punnayur Panchayath Phase III-Part IX-General Civil Work
Status On-going
District Thrissur
Executing Office Kunnamkulam Sn
Agreement Number
Agreement Date
TS Amount (Rs) 10000000
TS Number WRD/KWA-CE(CR)/EST_TS/18717/2023_5_1_1 Dated: 02-08-2023
Technical specification PWD Road Restoration -Punnayur Panchayath Phase III-Part IX-General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 05/09/2023
Scheduled date of Completion as per agreement 04 Dec 2023
Expected date of Completion 31/07/2024

Processing Dates

TS Date 02 Aug 2023
Estimate Approval 02 Aug 2023
NIT Approval 02 Aug 2023
Tender Closing 09 Aug 2023
Technichal Pre-Qualification 09 Aug 2023
Price bid opening 10 Aug 2023

Approval Dates

Workorder Date 05 Sep 2023
NA 18 Sep 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kunnamkulam PH Sn - AE
Date: 28/06/2024

Work has started | 0% Completed

Work order issued on 05/09/2023. Agreement executed on 18.09.2023 .

Kunnamkulam PH Sn - AE
Date: 27/06/2024

Work has started | 0% Completed

Work order issued on 05/09/2023. Agreement executed on 18.09.2023 .