JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.

Project JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.
Project Code PKDJJM102315938P1
Type Package
Main Project JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.Laying of 11.2km in addition
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 24300000
TS Number WRD/KWA/-CE(NR)/EST_TS/25947/2023_26_1_1
Technical specification Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.Laying of 11.2km in addition

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/12/2023
Scheduled date of Completion as per agreement 20 Aug 2024
Expected date of Completion 20/08/2024

Processing Dates

TS Date 23 Nov 2023
Estimate Approval 23 Nov 2023
NIT Approval 30 Nov 2023
Tender Closing 04 Dec 2023
Price bid opening 04 Dec 2023

Approval Dates

Workorder Date 21 Dec 2023
NA 04 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 29/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda).

Palakkad Proj AE 3
Date: 28/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda).