JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.
Project |
JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work. |
Project Code |
PKDJJM102315938 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.Laying of 11.2km in addition |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
28400000
|
AS Number |
G.O.(Rt)No.897/2023/WRD |
TS Amount (Rs) |
24300000 |
TS Number |
WRD/KWA/-CE(NR)/EST_TS/25947/2023_26_1_1 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
39564 |
Capacity in MLD |
12.00 |
Actual Project Completion Date |
20 Aug 2024 |
Coverage |
Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work.Laying of 11.2km in addition |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM - CWSS to Kanjirapuzha, Karakurussi and Tachampara Grama Panchayaths - Additional Works -Laying Distribution System in uncovered areas and shifting FHTCs in Karakurissi Panchayath General Civil work. |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jun 2024 |
Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda) |
Palakkad Proj AE 3 |
|
28 Jun 2024 |
Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda) |
Palakkad Proj AE 3 |
|
26 Jun 2024 |
Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda) |
Palakkad Proj AE 3 |
|
25 Jun 2024 |
Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda) |
Palakkad Proj AE 3 |
|
22 Jun 2024 |
Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda) |
Palakkad Proj AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/12/2023 |
Scheduled date of Completion of the Project |
20 Aug 2024 |
Expected date of Completion |
20/08/2024 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
23 Nov 2023 |