Palakkad Proj AE 3
Date: 29/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda)

Palakkad Proj AE 3
Date: 28/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda)

Palakkad Proj AE 3
Date: 26/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda)

Palakkad Proj AE 3
Date: 25/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda)

Palakkad Proj AE 3
Date: 22/06/2024

Work in progress | 24% Completed

Total laid till now- 5.462kms. Interconnection work of HDPE 90mm to Existing PVC of 90mm( ward-13 chullimunda)

Palakkad Proj AE 3
Date: 20/06/2024

Work in progress | 24% Completed

Total laid till now- 5.457kms. Interconnection work of HDPE ( ward-13 Mundampokk)

Palakkad Proj AE 3
Date: 18/06/2024

Work in progress | 24% Completed

Total laid till now- 5.457kms. Interconnection work of HDPE ( ward-13 Mundampokk)

Palakkad Proj AE 3
Date: 13/06/2024

Work in progress | 24% Completed

Total laid till now- 5.452kms. Interconnection work of HDPE ( ward-13 Chullimunda)

Palakkad Proj AE 3
Date: 08/06/2024

Work in progress | 24% Completed

Total laid till now- 5.448kms. Interconnection work of HDPE ( ward-13 Chullimunda)

Palakkad Proj AE 3
Date: 03/06/2024

Work in progress | 24% Completed

Total laid till now- 5.264kms. Today main line laid-150m ( ward-2 Vaduthalathottam)

Palakkad Proj AE 3
Date: 01/06/2024

Work in progress | 23% Completed

Total laid till now- 5.114kms.Today main line laid-80m ( ward-2 Vaduthalathottam)

Palakkad Proj AE 3
Date: 29/05/2024

Work in progress | 21% Completed

Total laid till now- 4.834kms.Today main line laid-144m ( ward-2 Vaduthalathottam)

Palakkad Proj AE 3
Date: 27/05/2024

Work in progress | 20% Completed

Total laid till now- 4.590Kms. Today main line laid-210m ( ward-2 Vaduthalathottam)

Palakkad Proj AE 3
Date: 22/05/2024

Work in progress | 16% Completed

Total laid till now- 3.810kms. Today main line laid-9m in Kottathamara & ward-4 mankurussi (Interconnection work of HDPE 90mm to existing PVC of 75mm)

Palakkad Proj AE 3
Date: 02/05/2024

Work in progress | 12% Completed

Total laid till now- 1.539kms. Today main line laid-332m in (Vazhempuram , Arappara )

Palakkad Proj AE 3
Date: 30/04/2024

Work in progress | 12% Completed

Today main line laid-250m in (Vazhempuram , Ayyappankavu ) 90mm HDPE PN 8-1.087 mts laied so far.

Palakkad Proj AE 3
Date: 23/04/2024

Work in progress | 11% Completed

Today main line laid-150m in Vazhempuram 90mm HDPE PN 8-362 mts

Palakkad Proj AE 3
Date: 22/04/2024

Work in progress | 10% Completed

Today main line laid-150m in Vazhempuram 90mm HDPE PN 8-150ms

Palakkad Proj AE 3
Date: 29/02/2024

Work in progress | 8% Completed

90mm PN-8 PE-100 HDPE Pipe 825 mts supplied.

Palakkad Proj AE 3
Date: 26/02/2024

Work in progress | 6% Completed

90mm PN-8 PE-100 HDPE Pipe-ISI - 1475 mts supplied.

Palakkad Proj AE 3
Date: 24/02/2024

Work in progress | 3% Completed

90mm PN-8 PE-100 HDPE Pipe-ISI 2700 mts supplied.

Palakkad Proj Dn AE 4
Date: 04/01/2024

Work in progress | 1% Completed

38/2023-24/SE/PHC/PKD Aggrement executed on 04/01/2024