Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath.
Project |
Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
Project Code |
PKDJJM102315857 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Project Dn |
AS Amount (Rs) |
50700000
|
AS Number |
897/2023/WRD |
TS Amount (Rs) |
29300000 |
TS Number |
CE(NR)/EST_TS/25942/2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
26462 |
Capacity in MLD |
21.00 |
Actual Project Completion Date |
21 Sep 2024 |
Coverage |
Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
Project Division Palakkad |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Jun 2024 |
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M |
Palakkad Proj AE 3 |
|
27 Jun 2024 |
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M |
Palakkad Proj AE 3 |
|
26 Jun 2024 |
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 402M. Total laid-456M |
Palakkad Proj AE 3 |
|
25 Jun 2024 |
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 282M. Total laid-336M |
Palakkad Proj AE 3 |
|
22 Jun 2024 |
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 102M. Total laid-156M |
Palakkad Proj AE 3 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/01/2024 |
Scheduled date of Completion of the Project |
21 Sep 2024 |
Expected date of Completion |
21/09/2024 |
Processing Dates
AS Date |
26 Oct 2023 |
TS Date |
29 Nov 2023 |