Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath.

Project Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath.
Project Code PKDJJM102315857P1
Type Package
Main Project Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath.
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 29300000
TS Number CE(NR)/EST_TS/25942/2023
Technical specification Additional laying of 10kms.Supplying & Laying of 90mm 8kg/cm2 HDPE Pipe 8000 metres and Supplying & Laying of 90mm 10kg/cm2 HDPE Pipe 2000 metres.BT Road Restoration of 8.0km & CC Road Restoration of 2.0km.
Contractor K RAMESHAN (Mob: 9447262192)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 08/01/2024
Scheduled date of Completion as per agreement 21 Sep 2024
Expected date of Completion 21/09/2024

Processing Dates

TS Date 29 Nov 2023
Estimate Approval 29 Nov 2023
Tender Closing 16 Dec 2023
Price bid opening 16 Dec 2023

Approval Dates

Workorder Date 08 Jan 2024
NA 22 Jan 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Palakkad Proj AE 3
Date: 28/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M.

Palakkad Proj AE 3
Date: 27/06/2024

Work in progress | 5% Completed

Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M.