Project | Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
---|---|
Project Code | PKDJJM102315857P1 |
Type | Package |
Main Project | Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Jal Jeevan Mission(JJM) - CWSS to Kanjirapuzha, Karakurissi and Thachampara Grama Panchayaths - ADDITIONAL WORKS - in THACHAMPARA Grama Panchayath. |
Status | On-going |
District | Palakkad |
Executing Office | Palakkad Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 29300000 |
TS Number | CE(NR)/EST_TS/25942/2023 |
Technical specification | Additional laying of 10kms.Supplying & Laying of 90mm 8kg/cm2 HDPE Pipe 8000 metres and Supplying & Laying of 90mm 10kg/cm2 HDPE Pipe 2000 metres.BT Road Restoration of 8.0km & CC Road Restoration of 2.0km. |
Contractor | K RAMESHAN (Mob: 9447262192) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/01/2024 |
---|---|
Scheduled date of Completion as per agreement | 21 Sep 2024 |
Expected date of Completion | 21/09/2024 |
TS Date | 29 Nov 2023 |
---|---|
Estimate Approval | 29 Nov 2023 |
Tender Closing | 16 Dec 2023 |
Price bid opening | 16 Dec 2023 |
Workorder Date | 08 Jan 2024 |
---|---|
NA | 22 Jan 2024 |
Palakkad Proj AE 3 |
Date: 28/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M.
Palakkad Proj AE 3 |
Date: 27/06/2024 |
Work in progress | 5% Completed
Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M.