Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M Palakkad Proj AE 3
27 Jun 2024 Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 498M. Total laid-552M Palakkad Proj AE 3
26 Jun 2024 Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 402M. Total laid-456M Palakkad Proj AE 3
25 Jun 2024 Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 282M. Total laid-336M Palakkad Proj AE 3
22 Jun 2024 Laying started.90mm PN 8 - 54M laid , 90mm PN 10 - 102M. Total laid-156M Palakkad Proj AE 3
20 Jun 2024 Laying started.90mm PN 8 - 54M laid. Palakkad Proj AE 3
20 Jun 2024 25 May 2024 Laying started.90mm PN 8 - 54M laid. Palakkad Proj AE 3
25 May 2024 Laying started.90mm PN 8 - 54M laid. Palakkad Project Dn EE
18 May 2024 Laying started.90mm PN 8 - 54M laid. Palakkad Proj AE 3
13 May 2024 Laying started.90mm PN 8 - 54M laid. Palakkad Proj AE 3