| Project | AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
|---|---|
| Project Code | KLMAMRUT112213227P1 |
| Type | Package |
| Main Project | AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 128700000 |
| TS Number | WRD/KWA-CE(SR)/EST_TS/610/2022_26_1_1 Dated: 07-01-2023 |
| Technical specification | 31.5 km line extension with JICA gap closing works, old line replacement and renovation of pukkulam 30.9 LL OHSR and 4122 FHTCs |
| Contractor | M S SANILKUMMAR (Mob: 9447234871) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 27/12/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 11 Dec 2024 |
| Expected date of Completion | 11/11/2024 |
| TS Date | 07 Jan 2023 |
|---|---|
| Estimate Approval | 01 Jan 2023 |
| NIT Approval | 12 Jan 2023 |
| Tender Closing | 03 Feb 2023 |
| Technichal Pre-Qualification | 06 Feb 2023 |
| Price bid opening | 10 Feb 2023 |
| Workorder Date | 28 Feb 2023 |
|---|---|
| NA | 12 Jun 2023 |
| Kollam Project HD |
| Date: 31/12/2024 |
Work has been completed | 100% Completed
Work completed on 21-12-2024. Line charging under progress....
| Kollam Project HD |
| Date: 30/12/2024 |
Work in progress | 90% Completed
Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc and chamber work in progress....