Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work.
Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work.
Project Code
MLPJJM022215777
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-01
Description
Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work.
Status
On-going
District
Malappuram
Executing Office
Edappal PH Dn
AS Amount (Rs)
3160200000
AS Number
G.O.(Rt)No.134/2022/WRD
TS Amount (Rs)
267700000
TS Number
WRD/KWA-CE(NR)/EST_TS/1088/2022_26_5_4
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
31 Mar 2025
Coverage
Packages
No.
Project Name
Location
View
1
Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work.
Edappal Sn
2
Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work.
Edappal Sn
3
Jal Jeevan Mission(JJM)-JJM -Phase 3-CWSS to Edappal and adjoining Panchayaths-Road Restoration -Panchayath BT rods after laying pipe line works in Alancode Panchayath.General civil work.
Edappal Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
28 Jan 2025
BT restoration completed, PWD road restoration and pipe laying works are progressing.
Edappal PH Dn EE
24 Jan 2025
BT restoration completed, PWD road restoration and pipe laying works are progressing.
Edappal Sn AE
20 Jan 2025
BT restoration completed, PWD road restoration and pipe laying works are progressing.
Edappal Sn AE
14 Jan 2025
BT restoration completed, PWD road restoration and pipe laying works are progressing.
Edappal Sn AE
06 Jan 2025
BT restoration completed, PWD road restoration and pipe laying works are progressing.