Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work.

Project Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work.
Project Code MLPJJM022215777P3
Type Package
Main Project Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work.
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work.
Status On-going
District Malappuram
Executing Office Edappal Sn
Agreement Number
Agreement Date
TS Amount (Rs) 11050000
TS Number WRD/KWA-CE(NR)/EST_TS/1088/2022_5_11_10
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement 14 Aug 2023
Expected date of Completion Date is not specified

Processing Dates

TS Date 03 Feb 2023
Estimate Approval 17 Dec 2022
NIT Approval 22 Feb 2022
Tender Closing 23 Jun 2023
Technichal Pre-Qualification 24 Jun 2023
Price bid opening 24 Jun 2023

Approval Dates

Workorder Date 17 Apr 2023
NA 10 May 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Edappal Sn AE
Date: 12/03/2025

Work in progress | 95% Completed

Chalissery - Valayamkulam road Partial Restoration Work (GSB and Wet Mix) completed, 500 mtr BM Work is pending. Othaloor - Pavittappuram road Completed. Bill under preparation..

Edappal PH Dn EE
Date: 01/03/2025

Work in progress | 51% Completed

Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.