Project | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work. |
---|---|
Project Code | MLPJJM022215777P3 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-PWD Road Restoration work in Chalisssery-Valayamkulam Road & amp; Othalur-Pavittapuram in Alancode Panchayath-General Civil Work. |
Status | On-going |
District | Malappuram |
Executing Office | Edappal Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 11050000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/1088/2022_5_11_10 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | 14 Aug 2023 |
Expected date of Completion | Date is not specified |
TS Date | 03 Feb 2023 |
---|---|
Estimate Approval | 17 Dec 2022 |
NIT Approval | 22 Feb 2022 |
Tender Closing | 23 Jun 2023 |
Technichal Pre-Qualification | 24 Jun 2023 |
Price bid opening | 24 Jun 2023 |
Workorder Date | 17 Apr 2023 |
---|---|
NA | 10 May 2023 |
Edappal Sn AE |
Date: 12/03/2025 |
Work in progress | 95% Completed
Chalissery - Valayamkulam road Partial Restoration Work (GSB and Wet Mix) completed, 500 mtr BM Work is pending. Othaloor - Pavittappuram road Completed. Bill under preparation..
Edappal PH Dn EE |
Date: 01/03/2025 |
Work in progress | 51% Completed
Chalissery Valayamkulam road GSB and wet mix completed, 500mtr BM pending to complete. Othaloor Pavittappuram road upto BM completed.