Project | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work. |
---|---|
Project Code | MLPJJM022215777P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work. |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Jal Jeevan Mission (JJM)-JJM-Phase 3-CWSS to Edappal and adjoining Panchayaths-Package 9-Laying distribution line and providing balance FHTCs in Alancode Grama Panchaayath-Pipeline work. |
Status | On-going |
District | Malappuram |
Executing Office | Edappal Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 267700000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/1088/2022_26_5_4 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/10/2023 |
---|---|
Scheduled date of Completion as per agreement | 09 Apr 2024 |
Expected date of Completion | Date is not specified |
TS Date | 11 May 2023 |
---|---|
Estimate Approval | 11 May 2023 |
NIT Approval | 07 Jun 2023 |
Tender Closing | 13 Feb 2023 |
Technichal Pre-Qualification | 08 Aug 2023 |
Price bid opening | 15 Feb 2023 |
Workorder Date | 01 Sep 2023 |
---|---|
NA | 08 Sep 2023 |
Edappal Sn AE |
Date: 12/03/2025 |
Work in progress | 38% Completed
Work in Progress. .
Edappal PH Dn EE |
Date: 01/03/2025 |
Work in progress | 38% Completed
Work in progress..