DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work

Project DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work
Project Code IDKGOK112217557
Type Main project
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work
Status Completed
District Idukki
Executing Office Nedumkandam Sn
AS Amount (Rs) 1325000
AS Number KRFB-PMU/MVPA-IDK/HH-PD/2021
TS Amount (Rs) 1320000
TS Number WRD/KWA-CE(CR)/EST_TS/13987/2022_26_3_2
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 700
Capacity in MLD 0.50
Actual Project Completion Date 21 Jan 2026
Coverage Parappu to Marykulam-

Packages

No. Project Name Location View
1 DEPOSIT-UTILITY SHIFTING - KRFB MVPA - IDUKKI-Hill Highway improvement Peerumedu Devikulam Road - RWSS to Marykulam Relaying pipes from Parappu to Marykulam-Pipeline Work Nedumkandam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Jan 2026 Pipe laying work and interconnection work all completed Nedumkandam Sn AE
18 Aug 2025 Pipes & specials are supplied, Laying works on-going Nedumkandam Sn AE
14 Aug 2025 Pipes & specials are supplied, Laying works on-going Nedumkandam Sn AE
11 Aug 2025 Pipes & specials are supplied, Laying works on-going Nedumkandam Sn AE
06 Aug 2025 Pipes & specials are supplied, Laying works on-going Nedumkandam Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/08/2023
Scheduled date of Completion of the Project 18 Aug 2024
Expected date of Completion 18/08/2025

Processing Dates

AS Date 22 Nov 2022
TS Date 02 May 2023

Other details