| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jan 2026 | Pipe laying work and interconnection work all completed | Nedumkandam Sn AE | |
| 18 Aug 2025 | Pipes & specials are supplied, Laying works on-going | Nedumkandam Sn AE | |
| 14 Aug 2025 | Pipes & specials are supplied, Laying works on-going | Nedumkandam Sn AE | |
| 11 Aug 2025 | Pipes & specials are supplied, Laying works on-going | Nedumkandam Sn AE | |
| 06 Aug 2025 | Pipes & specials are supplied, Laying works on-going | Nedumkandam Sn AE | |
| 16 Jul 2025 | Pipes & specials are supplied, Laying works on-going | Painavu PH Sub Dn AEE | |
| 21 Jun 2025 | Pipes & specials are supplied, Laying works on-going | Nedumkandam Sn AE |